PP-SHV Expressway to Be Completed Ahead of Schedule, First Free Ride Trial Set for September 2022

Construction of the Phnom Penh-Sihanoukville Expressway is scheduled to be completed ahead of schedule, changing from the initial date of March 2023 to September 2022, with a free ride trial during the first week or month. Meanwhile, construction is now over 55% complete.

Minister of Public Works and Transport HE Sun Chanthol said during an expressway site inspection on 21 June that the ministry is urging the company to speed up their construction so that it can be completed by September next year.

“After the completion, we will request the firm to allow us to drive on that route for free as a test, maybe for a week or a month, so that Cambodian people can enjoy our first expressway,” said HE Sun Chanthol.

Regarding the toll fee, the ministry is also currently negotiating for the firm to charge as low a fee as possible.

“Usually in foreign countries, they charge 10 cents to 15 cents per kilometre. However, we have urged the company not to charge that rate as it is quite expensive for Cambodia. Cambodia is a developing country, so in the first stage, the price should be somewhere below 10 cents,” said HE Sun Chanthol.

“The company can increase the price later after our economy and our standard of living is improving,” he added.

The Phnom Penh-Sihanoukville Expressway has a total length of 190 kilometres connecting Sangkat Samrong Krom, Khan Por Senchey in Phnom Penh to Sangkat 3 in Sihanoukville.

The project is expected to cost a total of US$2 billion and is being built by China Bridge and Road Corporation (CRBC) through the Cambodian PPSHV Expressway Co., Ltd.

- Video Advertisement -

Related Post

ADB demonstrates support for clean water development in Cambodia through a USD 400 million large-scale financing project by 2025

The Asian Development Bank (ADB) is committed to further strengthening urban development in Cambodia through the USD400 million Large-Scale Financing (MFF) project, which is scheduled for approval by the end of 2025. The initiative comes after the success of an ongoing USD119 million project in the Battambang and Kampong Cham provinces. This was stated in […]

The 250 km Cambodia Border Ring Road is starting the construction under FBID’s Nearly USD 27 Million

The Government of Cambodia opened the construction of a 250 km border ring road under the Foundation for Border Infrastructure Development (FBID) of USD 26,967.609 million on November 1, 2024, and is scheduled to be completed by the end of April 2027.a This was confirmed by HE Kim Bunthan, Chairman of the Working Group for […]

Blyncsy Publishes Map of U.S. Interstate Highways Showing Roadway Assets to Enhance Safety, Maintenance, and Accelerate the Digital Infrastructure Movement Nationally

Blyncsy empowers state DOTs with the ability to monitor and compare—in near real-time—the status of any major highway in the continental U.S. with their existing data for more informed decision-making. PHILADELPHIA — 2024 AASHTO Annual Meeting & Expo — October 29, 2024 — Blyncsy, a Bentley Systems Inc. (Nasdaq: BSY) company, today announced it published a comprehensive public […]

NR No. 10 Rehabilitation Nears Completion with 93% of Work Done and the Tallest Bridge Reaches 79% on Track for Operation in June 2025

By the end of October 2024, construction on Cambodia’s NR No. 10—a crucial route connecting the provinces of Koh Kong, Pursat, and Battambang—has reached an impressive 92.94% completion. Along this route, the tallest bridge, spanning 530 meters, has progressed to 79% completion and is set to be fully operational by June 2025, as reported by […]

Phnom Penh-SHV Expressway to Implement Full Toll Rates from 1 November

The Phnom Penh-Sihanoukville Expressway Company has confirmed it will transition to full toll rates beginning 1 November 2024, concluding a 20% discount period that will end at 00:00 on 31 October. This was detailed in the company’s official announcement, dated 31 October 2024. In continued support of smoother travel, the expressway company will offer Electronic […]

Major Wastewater Treatment Project to Begin on 30 Hectares in Takhmao City

The Ministry of Public Works and Transport has announced an ambitious plan to construct a comprehensive wastewater treatment system over a 30-hectare site in Prek They Village, Roka Khpos Commune, Takhmao City, Kandal Province. The project, which received formal approval during a meeting on 29 October 2024, will be managed under the guidance of HE […]