Gov’t Launches New Container Port in Kien Svay District

The Ministry of Public Works and Transport (MPWT) has officially launched the Phnom Penh Autonomous Port (PPAP)’s new container port in Banteay Dek commune, Kien Svay district, Kandal province, in response to growing container traffic.

According to the Phnom Penh Autonomous Port, this LM17 container port is the first stage of the third phase of port expansion.

The first phase covers 10 hectares of land with a capacity of 150,000 TEUs per year, built with a Chinese loan of US$28.9 million.

The second phase was built in 2018, which was an expansion of 4.5 hectares more with a capacity of 150,000 TEUs per year. The project used the investment capital from the issuance of securities and the savings budget of the Phnom Penh Autonomous Port.

Meanwhile, LM17 which is the first stage of the third phase began construction in late 2021. Covering 2.75 hectares of land with a capacity of 100,000 TEU per year, the project was built with an US$18.4 million budget from the saving and securities fund of PPAP.

Speaking at the inauguration ceremony on Monday 20 September, Minister of Public Works and Transport HE Sun Chanthol said that the LM17 Container Terminal is capable of transit containers up to 400,000 TEU per year.

The government will make an effort to expand the LM17 port to have a container capacity of 900,000 TEU per year to facilitate the transportation of goods to boost economic growth, he said.

According to PPAP, the second stage of the third phase will expand to port to handle 100,000 TEUs per year, bringing the total capacity of container handle at 500,000 TEUs per year.

- Video Advertisement -

Related Post

Japan’s JBIC Eyes Partnership for Major Infrastructure Development in Cambodia

The Japan Bank for International Cooperation (JBIC) has showcased a strong interest in collaborating on significant infrastructure projects in Cambodia. This development was announced following a meeting between Prime Minister Hun Manet and JBIC President and CEO Maeda Tadashi on May 28, 2025. During their discussions, President Maeda emphasized JBIC’s commitment to fostering partnerships with […]

The Government Announces New Opening Date for Techo International Airport

In a significant new update for travelers and the aviation industry, the State Secretariat of Civil Aviation has announced a revised opening date for the much-anticipated Techo International Airport in Takhmao. Originally set to open on July 10, 2025, the grand opening is now scheduled for September 9, 2025, as indicated in a notice issued […]

National Road 10 Completed: Enhancing Regional Connectivity

The construction of National Road 10, stretching over 197.36 kilometers, has been officially completed, marking a significant milestone in the region’s infrastructure development. The road is now fully operational and has undergone a thorough inspection by a team of skilled technicians to ensure its longevity and adherence to technical standards. A detailed assessment was conducted […]

Singapore Resumes Construction of Changi Airport’s Largest Passenger Terminal After Pandemic Delay

In a significant milestone for Singapore’s aviation sector, the construction of Terminal 5 (T5) at Changi Airport has officially commenced following a two-year pause brought on by the COVID-19 pandemic. The groundbreaking ceremony, which took place on May 14, 2025, was graced by Prime Minister Lawrence Wong. Prime Minister Wong highlighted that the new terminal […]

Doun Tri Dam Construction 97% Completion

  The construction of the Doun Tri Dam in Battambang province is now 97% complete, with final completion expected by October 2025. This significant infrastructure project, located in Rukkakiri district, is being financed through concessional loans from the Republic of Korea. During a project progress review led by His Excellency Tho Jetha, Minister of Water […]

Irrigation System Project in Banteay Meanchey and Battambang is 75% Completed

  Banteay Meanchey and Battambang provinces are making strides in agricultural development as the irrigation system construction project reaches a significant milestone. As of May 7, 2025, the project is 75% complete, thanks to financing from the Korean Eximbank. During a progress review meeting led by His Excellency Minister Tho Jetha, Minister of Water Resources […]