Bridge Across Mekong River in Kratie Province 55.8% Completed

As of early June 2024, the construction of the nearly 2 km long bridge across the Mekong River in Kratie province has reached 55.83% completion, while the connecting road is at 41.81%. This progress was announced on the official Facebook page of the Ministry of Public Works and Transport (MPWT) on 30 June 2024.

The MPWT confirmed that the 1,761-meter-long bridge spans the Mekong River between Chit Borey and Prek Prosop districts in Kratie province. The connecting road to Kratie City, spanning 33.459 kilometers, has reached 41.81% completion, whereas the bridge itself is at 55.83% completion as of June 2024.

Constructed by Shanghai Construction Group, the 1,761-meter-long and 13.55-meter-wide bridge, along with the 31.69-kilometer connecting road, is funded by the People’s Republic of China with an investment of US$111 million. The project is expected to take about 42 months to complete, significantly enhancing the region’s infrastructure and connectivity. (Read more)

- Video Advertisement -

Related Post

Darasakor International Airport Set for Temporary Opening in August

The Darasakor International Airport in Khemarak Phoumin City, Koh Kong Province, is scheduled to open temporarily at the end of August, initially operating domestic flights. This information was confirmed by Mr Sin Chanserivutha, Secretary of State and spokesperson for civil aviation, during a recent announcement to Fresh News in late June 2024. Mr. Chanserivutha stated […]

Historic 2,000 km Overland Convoy from China to Cambodia Marks Successful Inauguration of GMS Transit Facilitation

A convoy of seven Chinese trucks and passenger vehicles has successfully completed a historic journey of over 2,000 kilometres from China to Cambodia, marking the first implementation of the Greater Mekong Subregion (GMS) Transit Facilitation Agreement. The Ministry of Public Works and Transport announced the successful arrival of the convoy in Phnom Penh and the […]

Construction of NR No. 10 Reached 88.38% and Tallest Bridge Progressing Steadily, On Track for March 2025 Opening

As of the end of June 2024, the construction of NR No. 10, connecting Koh Kong, Pursat, and Battambang provinces, has reached 88.38% completion, while the tallest bridge, spanning 530 meters, has reached 43.50% completion. The road is slated for trial use by the end of March 2025, as per the latest update from the […]

Kampot International Tourism Port Set to Launch Operations in Q3 This Year

The Kampot International Tourism Port will commence temporary operations by the third quarter of 2024, operated by local firm AZ Builders Co., Ltd. This announcement follows an agreement signed on 28 June 2024 between H.E Peng Ponea, Minister of Public Works and Transport, and Mr Lim Bunsur, Chairman of AZ Builders Co., Ltd. “The firm […]

Hitachi Targets Southeast Asia Rail Market with $1.6 Billion Acquisition

Hitachi aims to expand its presence in Southeast Asia’s railway market following its $1.6 billion acquisition of Thales Group’s rail signal business on 31 May 2024, as China remains a dominant infrastructure supplier. This move enhances Hitachi’s ability to provide integrated railway solutions in Singapore and Malaysia. The announcement was made during a media roundtable […]

CFOCN Proposes Extensive Fibre Optic Network Installation Across Nine Cambodian Provinces

Cambodia Fiber Optic Communication Networks Co., Ltd (CFOCN) requested approval from the Ministry of Public Works and Transport to undertake a significant project involving the drilling and installation of fibre optic cables across nine major provinces. This request was discussed during a meeting chaired by Mr. Lim Sidenin, Secretary of State of the Ministry of […]