Progress Report: National Road No. 48 Restoration Nears Completion

The restoration and upgrade of National Road No. 48, stretching 148 kilometers from Sre Ambel to Koh Kong, has reached an impressive 78% completion as of the beginning of 2025, according to a statement from HE Phorn Rim, Spokesman of the Ministry of Public Works and Transport.

The ambitious project, which commenced on January 3, 2022, aims to significantly enhance the road’s quality, improving transportation, logistics, and tourism potential along this vital economic route. The total budget allocated for the project is approximately USD 78 million. (Read more and more)

HE Phorn Rim highlighted that the asphalt concrete (AC) ironing work will be finished by the end of the dry season in 2025. Some road sections have already been successfully completed, enhancing accessibility in the region.

As construction continues, HE Phorn Rim urged all road users, particularly heavy truck operators, to exercise caution and avoid overloading, especially on hilly sections. He also reminded taxi and passenger vehicle drivers to maintain a controlled speed to ensure their safety and that of others while helping to minimize dust on the roads.

National Road No. 48 is recognized as a key transportation artery for economic and trade activities, making its restoration crucial for the region’s development.

- Video Advertisement -

Related Post

Progress Report on National Road 5: Final Section Construction Updates

As of early February 2025, significant progress has been made on the final section of National Road 5, stretching from Seri Sophon to Poipet. With a total length of 35.14 kilometers, this crucial infrastructure project is currently 29% complete and is on track for completion in 2026. The update was shared by His Excellency Phon […]

Phnom Penh Infrastructure Project Advancing Rapidly to Combat Flooding

In a significant step towards enhancing urban resilience, a major infrastructure project targeting flood prevention in the western districts of Phnom Penh is now over 66% complete. The initiative, which focuses on installing large-scale box culverts, is actively transforming National Road 4 and surrounding areas. Managed by the PPPP-TCM joint venture, this ambitious project encompasses […]

Bavet City Takes a Major Step Towards Sustainability: Landfill Project Underway

In an exciting development for Bavet City, the construction of a significant landfill project has officially commenced on a sprawling 21-hectare site in Trang Mtes village, located in the heart of Svay Rieng province. The groundbreaking ceremony, held on January 31, 2025, began a transformative initiative to enhance the city’s environmental infrastructure. This project is […]

Japan Strengthens Cambodia’s Infrastructure with New Aid Package over USD 446K

In a significant move to bolster infrastructure development in Cambodia, the Japanese government has announced a generous aid package totaling USD 446,801 for three critical projects focusing on irrigation systems and bridge construction. HE Ueno Atsushi, Japan’s Ambassador to Cambodia, officially signed the grant agreement on 30th January alongside representatives from the three beneficiary institutions […]

National Road 7 Expansion Reaches 32% Completion

As of January 30, 2025, construction on the vital National Road 7 expansion project has reached a notable milestone, achieving 32.01% of its overall progress. The initiative, aimed at enhancing connectivity and promoting economic growth, focuses on upgrading the road to four lanes over a total span of 45.5 kilometers. The work stretches from the […]

Completion Progress on National Road No. 23 Reaches 70%

The ambitious construction project for the 20-kilometer stretch of National Road No. 23, linking Koh Thom and Loek Dek districts in Kandal province, has made significant headway, with approximately 70% of the work completed. According to a report by Cambodia National Television, the project is set to conclude in April 2025. His Excellency Phay Sovicheano, […]