Construction of Siem Reap-Angkor International Airport Project 44% Complete

The construction of Siem Reap-Angkor International Airport was 44% completed by the end of September 2022, as the company is accelerating work to meet the deadline by March 2023.

HE Sin Chansereyvutha, Under-Secretary of State and spokesman for the Secretariat of State for Civil Aviation, said on 20 October that the company is continuing construction as planned.

“The company is proceeding as planned so far, the company has completed 44% of the construction as of the end of September. In March 2023, the construction will be completed 100%, while in October 2023, the airport will be operational,” he said.

The construction of Siem Reap-Angkor International Airport started on 15 March 2020 and is scheduled to take a total construction period of 36 months at a cost of about US$880 million. (Read more)

The Siem Reap-Angkor International Airport project is built on an area of 700 hectares in Sot Nikum district, Siem Reap province, about 40 km from Angkor Park and about 50km from Siem Reap town.

When launched in October 2023, the airport will have a capacity of 7 million passengers per year.

- Video Advertisement -

Related Post

Techo International Airport Nears Completion: A New Gateway to Cambodia

In an exciting development for Cambodia’s aviation sector, the Techo International Airport construction project is now over 94% complete, with the total investment reaching nearly USD 1.4 billion. This ambitious project promises to transform the country’s skyways and enhance domestic and international travel connectivity. As of late December 2024, critical infrastructure components, including the Passenger […]

Chinese Company Pledges to Complete Mondulkiri Wind Power Station by 2026

In a significant commitment to renewable energy in Cambodia, HK OASIS Power Energy Development Co., Ltd. has vowed to complete the construction of a 150-megawatt wind power station in Mondulkiri province by 2026. This pledge was made by Mr. Wang Junwei, the company’s representative, during a meeting with HE Chea Vuthy, Secretary General of the […]

Serei Sophorn Welcomes the New 11 hectares of Landfill

In a significant development to enhance urban environmental management around the Tonle Sap Lake, the government officially inaugurated over 11 hectares of landfill on January 17, 2025. This project, part of the Phase 2 initiative, received support through a concessional loan from the Asian Development Bank (ADB). The landfill in Kangvea village of Sangkat Kampong […]

China Approves Highest & Largest Hydropower Dam in Tibet Worth USD 127 Billion Amid Global Concerns

China has approved the construction of the world’s largest hydropower dam on the lower Yarlung Tsangpo River in Tibet, with an estimated cost of USD 127 billion. The project, poised to generate three times more energy than the Three Gorges Dam, is expected to redefine renewable energy development globally but has raised significant concerns about […]

Cambodia Welcomes 17 New Investment Projects Worth USD 150 Million in January 2025

In an exciting start to the year, Cambodia’s investment landscape is poised for growth as the country received a notable infusion of capital with 17 new investment projects. These initiatives, collectively valued at approximately USD 150 million, were registered during the inaugural “One Window Service Office” (OWSO) meeting for 2025, held on 15 January, chaired […]

Progress Update on Kampong Thom Dam Project: 25% Completion Mark Achieved

Construction on the Kampong Kor Dam is progressing steadily, with 25% of the project now completed. HE Chan Sinath, Secretary of State, provided this update during an inspection of the project on 12 January 2025. During the inspection, HE Chan Sinath outlined the project’s current status, specifying that the dam’s construction has reached 10%, while […]