NR 33 Rehabilitation Gains Momentum: 40% Completion Ready for Sea Festival

Progress on the rehabilitation of Cambodia’s vital National Road 33 is well underway, with completion inching closer to reality. As of 27 October 2023, the ambitious project, aimed at enhancing the quality of this crucial transport artery, has reached nearly 40% completion. This substantial achievement underscores the government’s commitment to ensuring the road is ready for the upcoming Sea Festival.

A recent site visit led by HE Pal Chandara, Secretary of State of the Ministry of Public Works and Transport, along with a technical working group from China Bridge and Road Corporation (CRBC) and a representative from Guangzhou Wang An Technical Advisory Company, provided an opportunity to assess progress.

The project’s advancements are impressive, with key milestones already met:

  1. Road Widening: Approximately 52.57 kilometres of the road have been cleared and widened to accommodate the growing traffic demands.
  2. Sub-grade Work: An impressive 49.87 kilometres of sub-grade work have been successfully executed, ensuring a solid foundation for the road.
  3. Sub-Base Paving: The sub-base has been paved over 37.66 kilometres, enhancing the road’s structural integrity.

HE Secretary of State Pal Chandara has emphasised the importance of maintaining safety on-site. Measures include prominently placed warning signs, traffic diversion signs, and adequate safety equipment to facilitate the movement of goods and people. Ensuring the well-being of the local community is a priority, particularly as preparations intensify for the forthcoming Sea Festival.

This extensive project, designed to revitalise National Road 33, has been allocated more than US$61 million in funding. This funding comprises a concessional loan from the Government of the People’s Republic of China, supplemented by the contributions of the Royal Government of Cambodia, which is earmarked for mitigating impacts and taxes. (Read more)

- Video Advertisement -

Related Post

Kampong Cham Province Achieved Significant Infrastructure Development in 2024

In a remarkable stride towards improving its infrastructure, Kampong Cham Province has completed over 119 kilometers of road construction in 2024. This achievement was announced by HE Un Chanda, the Governor of Kampong Cham Province, during a press conference. During the year 2024 alone, the province welcomed 27 projects aimed at developing DBST (Dense Bituminous […]

Major Progress Made on Flood Prevention in Western Phnom Penh

In a significant step towards mitigating flooding in western Phnom Penh, the ambitious drainage and drainage system restoration project has reached a milestone, now standing at 50.50% completion as of January 5, 2025. This essential infrastructure initiative, spearheaded by the General Department of Wastewater Treatment System under the Ministry of Public Works and Transport, aims […]

National Road 7 Expansion Project Progresses, Reaches 28.76% Completion

In a significant step towards enhancing Cambodia’s infrastructure, the ambitious project to restore and expand National Road No. 7 has reached an impressive 28.76% completion as of early January 2025. This major development was confirmed during a thorough inspection led by HE Lim Sidenin, Secretary of State of the Ministry of Public Works and Transport, […]

Progress Report: National Road No. 48 Restoration Nears Completion

The restoration and upgrade of National Road No. 48, stretching 148 kilometers from Sre Ambel to Koh Kong, has reached an impressive 78% completion as of the beginning of 2025, according to a statement from HE Phorn Rim, Spokesman of the Ministry of Public Works and Transport. The ambitious project, which commenced on January 3, […]

Major Infrastructure Development Takes Shape in Kandal Province

The China Road and Bridge Corporation (CRBC) is swiftly constructing a temporary steel bridge in Kandal province to facilitate drilling for a vital clay-stone bridge. HE Phorn Rim, the Ministry of Public Works and Transport spokesman, confirmed that this project aims to improve connectivity between the eastern outskirts of Phnom Penh and Xi Jinping Boulevard. […]

What has the border ring road construction project achieved two months after the construction site opened?

The project to build the border ring road, funded by nearly $27 million from the Border Infrastructure Fund, has made significant progress since the construction site opened on November 4, 2024.  Here are some key achievements of this historic project for Cambodia: Demining Operations: The team successfully cleared 1,462,500 square meters of unexploded ordnance, with […]