Vital Irrigation & Drainage Rehabilitation Project in Southwest Phnom Penh 10% Complete

The Roleang Chrey and Stung Bati sub-projects of the Irrigation and Drainage Improvement and Rehabilitation Project in the southwest of Phnom Penh have successfully achieved a commendable 10% completion. This milestone was reported by the Ministry of Water Resources and Meteorology (MoWRM) on 30 January 2024.

During his visit to the project sites, HE Minister Tho Chetha emphasized the crucial role of this initiative in responding to water shortages in the Chbar Morn, Samrong Tong, and Kong Pisey districts of Kampong Speu province, caused by the closure of the Roleang Chrey River. The minister highlighted the collaborative efforts of the Ministry of Water Resources and Meteorology MoWRM, the Provincial Department of Water Resources, relevant authorities, and the Japan International Cooperation Agency (JICA) in ensuring a reliable water supply for the affected regions. As part of the intervention, the main Rolang Chrey water gate was reopened, benefitting local farmers and safeguarding irrigation systems.

The Irrigation and Drainage Improvement and Rehabilitation Project in Phnom Penh’s southwest comprises two essential sub-projects. The first, the Rolang Chrey sub-project, spans Chbar Morn City and Samrong Tong district in Kampong Speu province, covering 12.60km and involving 207 related constructions. The second sub-project, Kandal Stung Bati, is situated in Kandal Steung district, Kandal Province, and Bati district, Takeo Province, with a 4km concrete canal diverting water from Stung Prek Tnaot and Stung Touch to Tonle Bati. This sub-project includes 33 related structures.

Commencing on 13 June 2023, with generous development assistance from Japan, this pivotal irrigation and drainage rehabilitation project is scheduled for completion in June 2026, underscoring its long-term commitment to bolstering Cambodia’s agricultural infrastructure and ensuring water security for the region. (Read more)

- Video Advertisement -

Related Post

Progress Update on the Bassac River Bridge Project: 19% Completion Marked

The ambitious project to construct a bridge across the Bassac River has achieved a significant milestone, with 19% of the work now completed after 11 months of construction. The project, which connects Chak Angre Krom and Prek Pra, remains on schedule, with no delays reported, according to a Ministry of Public Works and Transport statement. […]

Progress Report on National Road 5: Final Section Construction Updates

As of early February 2025, significant progress has been made on the final section of National Road 5, stretching from Seri Sophon to Poipet. With a total length of 35.14 kilometers, this crucial infrastructure project is currently 29% complete and is on track for completion in 2026. The update was shared by His Excellency Phon […]

Phnom Penh Infrastructure Project Advancing Rapidly to Combat Flooding

In a significant step towards enhancing urban resilience, a major infrastructure project targeting flood prevention in the western districts of Phnom Penh is now over 66% complete. The initiative, which focuses on installing large-scale box culverts, is actively transforming National Road 4 and surrounding areas. Managed by the PPPP-TCM joint venture, this ambitious project encompasses […]

Bavet City Takes a Major Step Towards Sustainability: Landfill Project Underway

In an exciting development for Bavet City, the construction of a significant landfill project has officially commenced on a sprawling 21-hectare site in Trang Mtes village, located in the heart of Svay Rieng province. The groundbreaking ceremony, held on January 31, 2025, began a transformative initiative to enhance the city’s environmental infrastructure. This project is […]

Japan Strengthens Cambodia’s Infrastructure with New Aid Package over USD 446K

In a significant move to bolster infrastructure development in Cambodia, the Japanese government has announced a generous aid package totaling USD 446,801 for three critical projects focusing on irrigation systems and bridge construction. HE Ueno Atsushi, Japan’s Ambassador to Cambodia, officially signed the grant agreement on 30th January alongside representatives from the three beneficiary institutions […]

National Road 7 Expansion Reaches 32% Completion

As of January 30, 2025, construction on the vital National Road 7 expansion project has reached a notable milestone, achieving 32.01% of its overall progress. The initiative, aimed at enhancing connectivity and promoting economic growth, focuses on upgrading the road to four lanes over a total span of 45.5 kilometers. The work stretches from the […]