The rapid progress of riverbank construction in Kampong Cham has reached 65%

In a remarkable display of swift action and engineering prowess, the construction of a vital riverbank in the Srey Santhor district has surged ahead, reaching an impressive 65% completion in under a month.

The Moan Dob Leu village project, Meanchey commune, commenced on December 23, 2024, following the alarming collapse of the Mekong River bank behind Wat Sotsanaream on October 17, 2024. The Ministry of Water Resources and Meteorology has proactively addressed the urgency of the situation, recognizing the vulnerability of the fine sand to the relentless flow of water.

According to the latest report from the Ministry, as of January 7, 2025, over 200 meters of the river bank have been fortified. Key progress highlights include 100% completion in protecting the lower bank and significant advancements in stabilizing the slope with sandbags, reaching 35% completion.

The construction is strategically divided into two phases. The first phase focuses on securing the lower leg with geotextile sandbags, while the second phase will aim to reinforce the upper bank once the lower foundation is secure. This careful planning reflects the commitment to ensuring the safety and sustainability of the riverbank for years to come.

As the community watches the construction unfold, there is a sense of relief and hope that this initiative will protect local residents and their livelihoods from the risk of future erosion. The Ministry’s timely intervention highlights the importance of responsible water management and infrastructure development in safeguarding our natural resources.

- Video Advertisement -

Related Post

Kampong Cham Province Achieved Significant Infrastructure Development in 2024

In a remarkable stride towards improving its infrastructure, Kampong Cham Province has completed over 119 kilometers of road construction in 2024. This achievement was announced by HE Un Chanda, the Governor of Kampong Cham Province, during a press conference. During the year 2024 alone, the province welcomed 27 projects aimed at developing DBST (Dense Bituminous […]

Major Progress Made on Flood Prevention in Western Phnom Penh

In a significant step towards mitigating flooding in western Phnom Penh, the ambitious drainage and drainage system restoration project has reached a milestone, now standing at 50.50% completion as of January 5, 2025. This essential infrastructure initiative, spearheaded by the General Department of Wastewater Treatment System under the Ministry of Public Works and Transport, aims […]

National Road 7 Expansion Project Progresses, Reaches 28.76% Completion

In a significant step towards enhancing Cambodia’s infrastructure, the ambitious project to restore and expand National Road No. 7 has reached an impressive 28.76% completion as of early January 2025. This major development was confirmed during a thorough inspection led by HE Lim Sidenin, Secretary of State of the Ministry of Public Works and Transport, […]

Progress Report: National Road No. 48 Restoration Nears Completion

The restoration and upgrade of National Road No. 48, stretching 148 kilometers from Sre Ambel to Koh Kong, has reached an impressive 78% completion as of the beginning of 2025, according to a statement from HE Phorn Rim, Spokesman of the Ministry of Public Works and Transport. The ambitious project, which commenced on January 3, […]

Major Infrastructure Development Takes Shape in Kandal Province

The China Road and Bridge Corporation (CRBC) is swiftly constructing a temporary steel bridge in Kandal province to facilitate drilling for a vital clay-stone bridge. HE Phorn Rim, the Ministry of Public Works and Transport spokesman, confirmed that this project aims to improve connectivity between the eastern outskirts of Phnom Penh and Xi Jinping Boulevard. […]

What has the border ring road construction project achieved two months after the construction site opened?

The project to build the border ring road, funded by nearly $27 million from the Border Infrastructure Fund, has made significant progress since the construction site opened on November 4, 2024.  Here are some key achievements of this historic project for Cambodia: Demining Operations: The team successfully cleared 1,462,500 square meters of unexploded ordnance, with […]