Rapid Progress of Riverbank Construction in Kampong Cham Achieves 65%

In a remarkable display of swift action and engineering prowess, the construction of a vital riverbank in the Srey Santhor district has surged ahead, reaching an impressive 65% completion in under a month.

The project in Moan Dob Leu village, Meanchey commune, commenced on 23 December 2024, following the alarming collapse of the Mekong River bank behind Wat Sotsanaream on 12 October 2024. The Ministry of Water Resources and Meteorology has proactively addressed the urgency of the situation, recognizing the vulnerability of the fine sand to the relentless flow of water.

According to the latest report from the ministry, as of 7 January 2025, over 200 meters of the river bank have been fortified. Key progress highlights include 100% completion in protecting the lower bank and significant advancements in stabilizing the slope with sandbags, reaching 35% completion.

The construction is strategically divided into two phases. The first phase focuses on securing the lower leg with geotextile sandbags, while the second phase will aim to reinforce the upper bank once the lower foundation is secure. This careful planning reflects the commitment to ensuring the safety and sustainability of the riverbank for years to come.

As the community watches the construction unfold, there is a sense of relief and hope that this initiative will protect local residents and their livelihoods from the risk of future erosion. The ministry’s timely intervention highlights the importance of responsible water management and infrastructure development in safeguarding our natural resources.

- Video Advertisement -

Related Post

Progress Update on the Bassac River Bridge Project: 19% Completion Marked

The ambitious project to construct a bridge across the Bassac River has achieved a significant milestone, with 19% of the work now completed after 11 months of construction. The project, which connects Chak Angre Krom and Prek Pra, remains on schedule, with no delays reported, according to a Ministry of Public Works and Transport statement. […]

Progress Report on National Road 5: Final Section Construction Updates

As of early February 2025, significant progress has been made on the final section of National Road 5, stretching from Seri Sophon to Poipet. With a total length of 35.14 kilometers, this crucial infrastructure project is currently 29% complete and is on track for completion in 2026. The update was shared by His Excellency Phon […]

Phnom Penh Infrastructure Project Advancing Rapidly to Combat Flooding

In a significant step towards enhancing urban resilience, a major infrastructure project targeting flood prevention in the western districts of Phnom Penh is now over 66% complete. The initiative, which focuses on installing large-scale box culverts, is actively transforming National Road 4 and surrounding areas. Managed by the PPPP-TCM joint venture, this ambitious project encompasses […]

Bavet City Takes a Major Step Towards Sustainability: Landfill Project Underway

In an exciting development for Bavet City, the construction of a significant landfill project has officially commenced on a sprawling 21-hectare site in Trang Mtes village, located in the heart of Svay Rieng province. The groundbreaking ceremony, held on January 31, 2025, began a transformative initiative to enhance the city’s environmental infrastructure. This project is […]

Japan Strengthens Cambodia’s Infrastructure with New Aid Package over USD 446K

In a significant move to bolster infrastructure development in Cambodia, the Japanese government has announced a generous aid package totaling USD 446,801 for three critical projects focusing on irrigation systems and bridge construction. HE Ueno Atsushi, Japan’s Ambassador to Cambodia, officially signed the grant agreement on 30th January alongside representatives from the three beneficiary institutions […]

National Road 7 Expansion Reaches 32% Completion

As of January 30, 2025, construction on the vital National Road 7 expansion project has reached a notable milestone, achieving 32.01% of its overall progress. The initiative, aimed at enhancing connectivity and promoting economic growth, focuses on upgrading the road to four lanes over a total span of 45.5 kilometers. The work stretches from the […]