NR No. 10 Rehabilitation Nears Completion with 93% of Work Done & Tallest Bridge Reaches 79% on Track for Operation in June 2025

By the end of October 2024, construction on Cambodia’s NR No. 10—a crucial route connecting the provinces of Koh Kong, Pursat, and Battambang—has reached an impressive 92.94% completion. Along this route, the tallest bridge, spanning 530 meters, has progressed to 79% completion and is set to be fully operational by June 2025, as reported by HE Bong Bun Hourn, Secretary of State of the Ministry of Public Works and Transport, following an official site inspection on 1 November 2024.

The road is partially open to traffic, but travelers are advised to exercise caution as certain sections remain unpaved and prone to slipping during heavy rains. Currently, the road surface varies across the route’s 198.518-kilometer stretch, with key sections comprising rubberized surfaces and red gravel. Specifically, the road’s condition is as follows:

  • PK0 (Samlot) to PK60 (Two Crocodiles): Rubber surface
  • PK60 to PK85: Red gravel
  • PK85 to PK112 (Osom): Rubber surface
  • PK112 to PK130: Red gravel (some areas prone to slipping in rain)
  • PK130 to PK160: Rubber surface
  • PK160 to PK175: Red gravel
  • PK175 to PK198 (Koh Kong): Rubber surface

NR No. 10 has been classified as a Grade III double-paved road (DBST) and measures 9 meters wide. The rehabilitation project, which represents a vital improvement in connectivity in the region, has been financed by the Chinese government at a total cost exceeding USD 188 million. (Read more)

- Video Advertisement -

Related Post

Twin Flyovers Near Completion at Phnom Penh-Kandal Border

  The construction of the Samdech Thipadei Hun Manet flyover, connecting Phnom Penh and Kandal province, has reached an impressive milestone with 85% of the project completed. The latest update comes as the twin flyovers advance toward the final stages of construction. A significant ceremony marking the connection of the bridge body was held on […]

Major Infrastructure Project Nears Completion in Siem Reap

A significant infrastructure development is underway in Siem Reap province, with a 15-kilometer road connecting National Road 6 to the Kampong Phluok tourist area now approximately 70% complete, according to an announcement from the Siem Reap administration. This vital roadway, which measures 8 meters in width, is part of a project initiated by Prime Minister […]

Japan’s JBIC Eyes Partnership for Major Infrastructure Development in Cambodia

The Japan Bank for International Cooperation (JBIC) has showcased a strong interest in collaborating on significant infrastructure projects in Cambodia. This development was announced following a meeting between Prime Minister Hun Manet and JBIC President and CEO Maeda Tadashi on May 28, 2025. During their discussions, President Maeda emphasized JBIC’s commitment to fostering partnerships with […]

The Government Announces New Opening Date for Techo International Airport

In a significant new update for travelers and the aviation industry, the State Secretariat of Civil Aviation has announced a revised opening date for the much-anticipated Techo International Airport in Takhmao. Originally set to open on July 10, 2025, the grand opening is now scheduled for September 9, 2025, as indicated in a notice issued […]

National Road 10 Completed: Enhancing Regional Connectivity

The construction of National Road 10, stretching over 197.36 kilometers, has been officially completed, marking a significant milestone in the region’s infrastructure development. The road is now fully operational and has undergone a thorough inspection by a team of skilled technicians to ensure its longevity and adherence to technical standards. A detailed assessment was conducted […]

Singapore Resumes Construction of Changi Airport’s Largest Passenger Terminal After Pandemic Delay

In a significant milestone for Singapore’s aviation sector, the construction of Terminal 5 (T5) at Changi Airport has officially commenced following a two-year pause brought on by the COVID-19 pandemic. The groundbreaking ceremony, which took place on May 14, 2025, was graced by Prime Minister Lawrence Wong. Prime Minister Wong highlighted that the new terminal […]