Three Sections of NR5 Expansion 46%, 38%, and 97% Complete, Respectively

To date, the renovation of NR5 is approximately 60% complete, with the southern part Prek Kdam- Pursat at 46.05%, the central part Pursat-Battambang at 38.08%, and the northern part Battambang-Banteay Meanchey at 97.30%.

This is according to a meeting between the Ministry of Public Works and Transport and the Ministry of Economy and Finance on 1 June.

Besides providing the updated progress, the meeting also officially opened the bidding for the construction of the Serei Sophorn-Poipet section (34 km) and the bidding for the construction of the vehicle weighing stations.

The renovation of NR5 has a total length of 366km connecting the capital to the northwestern part of the country passing through Kompong Chhnang, Pursat, Battambang, and Banteay Meanchey provinces.

The road will be upgraded to Asphalt Concrete (AC) and expanded to four lanes with a width of 23m. The project is being undertaken with a loan of US$500 million from the Japanese government.

In addition to the road upgrade, the Ministry of Public Works and Transport is also planning to utilise AI technology to control traffic system, especially the overweight vehicles on NR5 after the completion. (Read more)

The technology is known as the AI Camera and Weigh-in-Motion Sensor Centralised Database Solution System. The system will automatically report the data by just driving through the spot where the system is installed, which would make it easier for officers to monitor and crack down on any overweight trucks.

- Video Advertisement -

Related Post

China Construction America Ordered to Pay US$1.6 Billion and Conflict of Political Interests Behind

A New York court has ordered China Construction America Inc. (CCA), a subsidiary of Chinese state-owned China State Construction Engineering, to pay US$1.6 billion to BML Properties, the original owner of the Baha Mar casino resort in the Bahamas, after the contractor was found to have committed “many acts of fraud” during its takeover of […]

Phnom Penh-SHV Expressway Offers Exclusive Discounts for 3-Day Water Festival Celebration

To celebrate the Royal Water Festival from 14 to 16 November 2024, the Ministry of Public Works and Transport (MPWT) has announced a special three-day discount on the Phnom Penh-Sihanoukville Expressway. Notification No. 052 S.K.R., dated 12 November 2024, confirmed that the Phnom Penh-Sihanoukville Expressway Company will offer a 20% discount on toll fees for […]

Groundbreaking of 500-Hectare Green Textile Industrial Park in Kampong Speu to Create Up to 60K Jobs

A groundbreaking ceremony on 8 November 2024 marked the start of a 500-hectare green textile industrial park in Chheu Neang Village, Taing Sya Commune, Phnom Sruoch District, Kampong Speu. Attended by HE Heng Sour, Minister of Labor and Vocational Training, HE Dr. Cheam Chansophoan, Governor of Kampong Speu Province, and Mr. John Yu, Chairman of […]

PM Inaugurates USD10 Million Techo Santepheap Ankoul Beach Road to Boost Tourism in Kep

The USD10 million Techo Santepheap Ankoul Road project, aimed at enhancing tourism infrastructure, was officially inaugurated in Ang Kol, Kep Village, and Angkor Village within the Ang Koul Commune of Damnak Chang Eur District, Kep Province. Led by PM Samdech Hun Manet, the ceremony on 11 November 2024 marked the completion of this pivotal project […]

NR No. 33 (Kampot-Chrak Lok) Reaches 99% Completion, Strengthening Provincial Transport Network

NR No. 33, connecting Kampot to Chrak Lok, is on the cusp of completion, with an impressive 98.89% of the project finalised as of early November 2024. This achievement was highlighted in an official inspection conducted on 6 November 2024 by HE Pal Chandara, Secretary of State of the Ministry of Public Works and Transport, […]

Techo Int’l Airport Nears Completion at Over 90%, Already Costs USD 1.3 Billion

The Techo International Airport project has surpassed 90% completion as of early November 2024, with construction costs exceeding USD 1.3 billion. This milestone was announced by HE Sinn Chansery Vutha, Secretary of State and Spokesman for the Secretariat of State for Civil Aviation, on 6 November 2024. HE confirmed that major construction will conclude by […]