Construction of NR2 & NR22 Delayed Further

The contracted firm building NR2 and NR22 has asked for another four-month project completion delay, citing a lack of construction machinery.

HE Sun Chanthol, Minister of Public Works and Transport, said on 9 February that the ministry is evaluating the request.

“The construction company has asked for a delay of about 4 months. We have not yet approved. A proper technical evaluation and the reasons why the construction works of NR 2 and 22 are slower than planned are needed,” said HE Chanthol.

According to the plan, the construction of NR2 will be completed in April 2022, but to date, it has been just 47.95% completed.

NR2 has a total length of 62.56 km from Takhmao roundabout to Daun Keo roundabout in Takeo province and NR22 has a total length of 9.61 km from Daun Keo roundabout to Ang Ta Som, NR3.

With ground broken in early 2020, both projects are being built under a US$56 million budget, which is jointly financed by the South Korean government and Cambodian government budget. (Read more)

- Video Advertisement -

Related Post

China Construction America Ordered to Pay US$1.6 Billion and Conflict of Political Interests Behind

A New York court has ordered China Construction America Inc. (CCA), a subsidiary of Chinese state-owned China State Construction Engineering, to pay US$1.6 billion to BML Properties, the original owner of the Baha Mar casino resort in the Bahamas, after the contractor was found to have committed “many acts of fraud” during its takeover of […]

The Gov’t announces a 3-day discount on the Phnom Penh-Sihanoukville Expressway

The Ministry of Public Works and Transport (MPWT) has announced a three-day discount on the Phnom Penh-Sihanoukville Expressway to celebrate the Royal Water Festival, floating lanterns, and moon worshiping, which will take place from November 14 to November 16, 2024. This announcement was made in notification No. 052 S.K.R. dated November 12, 2024. During this […]

Groundbreaking of 500-Hectare Green Textile Industrial Park in Kampong Speu to Create Up to 60K Jobs

A groundbreaking ceremony on 8 November 2024 marked the start of a 500-hectare green textile industrial park in Chheu Neang Village, Taing Sya Commune, Phnom Sruoch District, Kampong Speu. Attended by HE Heng Sour, Minister of Labor and Vocational Training, HE Dr. Cheam Chansophoan, Governor of Kampong Speu Province, and Mr. John Yu, Chairman of […]

PM Inaugurates USD10 Million Techo Santepheap Ankoul Beach Road to Boost Tourism in Kep

The USD10 million Techo Santepheap Ankoul Road project, aimed at enhancing tourism infrastructure, was officially inaugurated in Ang Kol, Kep Village, and Angkor Village within the Ang Koul Commune of Damnak Chang Eur District, Kep Province. Led by PM Samdech Hun Manet, the ceremony on 11 November 2024 marked the completion of this pivotal project […]

NR No. 33 (Kampot-Chrak Lok) Reaches 99% Completion, Strengthening Provincial Transport Network

NR No. 33, connecting Kampot to Chrak Lok, is on the cusp of completion, with an impressive 98.89% of the project finalised as of early November 2024. This achievement was highlighted in an official inspection conducted on 6 November 2024 by HE Pal Chandara, Secretary of State of the Ministry of Public Works and Transport, […]

Techo Int’l Airport Nears Completion at Over 90%, Already Costs USD 1.3 Billion

The Techo International Airport project has surpassed 90% completion as of early November 2024, with construction costs exceeding USD 1.3 billion. This milestone was announced by HE Sinn Chansery Vutha, Secretary of State and Spokesman for the Secretariat of State for Civil Aviation, on 6 November 2024. HE confirmed that major construction will conclude by […]