Construction of NR2 & NR22 Delayed Further

The contracted firm building NR2 and NR22 has asked for another four-month project completion delay, citing a lack of construction machinery.

HE Sun Chanthol, Minister of Public Works and Transport, said on 9 February that the ministry is evaluating the request.

“The construction company has asked for a delay of about 4 months. We have not yet approved. A proper technical evaluation and the reasons why the construction works of NR 2 and 22 are slower than planned are needed,” said HE Chanthol.

According to the plan, the construction of NR2 will be completed in April 2022, but to date, it has been just 47.95% completed.

NR2 has a total length of 62.56 km from Takhmao roundabout to Daun Keo roundabout in Takeo province and NR22 has a total length of 9.61 km from Daun Keo roundabout to Ang Ta Som, NR3.

With ground broken in early 2020, both projects are being built under a US$56 million budget, which is jointly financed by the South Korean government and Cambodian government budget. (Read more)

- Video Advertisement -

Related Post

The rapid progress of riverbank construction in Kampong Cham has reached 65%

In a remarkable display of swift action and engineering prowess, the construction of a vital riverbank in the Srey Santhor district has surged ahead, reaching an impressive 65% completion in under a month. The Moan Dob Leu village project, Meanchey commune, commenced on December 23, 2024, following the alarming collapse of the Mekong River bank […]

Kampong Cham Province Achieved Significant Infrastructure Development in 2024

In a remarkable stride towards improving its infrastructure, Kampong Cham Province has completed over 119 kilometers of road construction in 2024. This achievement was announced by HE Un Chanda, the Governor of Kampong Cham Province, during a press conference. During the year 2024 alone, the province welcomed 27 projects aimed at developing DBST (Dense Bituminous […]

Major Progress Made on Flood Prevention in Western Phnom Penh

In a significant step towards mitigating flooding in western Phnom Penh, the ambitious drainage and drainage system restoration project has reached a milestone, now standing at 50.50% completion as of January 5, 2025. This essential infrastructure initiative, spearheaded by the General Department of Wastewater Treatment System under the Ministry of Public Works and Transport, aims […]

National Road 7 Expansion Project Progresses, Reaches 28.76% Completion

In a significant step towards enhancing Cambodia’s infrastructure, the ambitious project to restore and expand National Road No. 7 has reached an impressive 28.76% completion as of early January 2025. This major development was confirmed during a thorough inspection led by HE Lim Sidenin, Secretary of State of the Ministry of Public Works and Transport, […]

Progress Report: National Road No. 48 Restoration Nears Completion

The restoration and upgrade of National Road No. 48, stretching 148 kilometers from Sre Ambel to Koh Kong, has reached an impressive 78% completion as of the beginning of 2025, according to a statement from HE Phorn Rim, Spokesman of the Ministry of Public Works and Transport. The ambitious project, which commenced on January 3, […]

Major Infrastructure Development Takes Shape in Kandal Province

The China Road and Bridge Corporation (CRBC) is swiftly constructing a temporary steel bridge in Kandal province to facilitate drilling for a vital clay-stone bridge. HE Phorn Rim, the Ministry of Public Works and Transport spokesman, confirmed that this project aims to improve connectivity between the eastern outskirts of Phnom Penh and Xi Jinping Boulevard. […]