Construction of Third Ring Road 80% Completed by October

The construction of the US$267-million third ring road was about 77% complete as of October, while the construction of the bridge across the Bassac River has been 88% completed, according to the Ministry of Public Works and Transport.

The progress of the construction of the third ring road was presented by HE Sun Chanthol, Senior Minister, Minister of Public Works and Transport, at a press conference at the Government Spokesman’s Unit held on 27 October.

The construction of the third ring road project​ began on 14 January 2019, built by Shanghai Construction Group Co., Ltd at a cost of US$267 million, under concessional financing from China and a contribution fund from the Royal Government of Cambodia to deal with the impact of demining.

The third ring road has a total length of 52 km, is 22 meters wide, and with 4 lanes, which connect NR6 to NR1 passing through NR 5, 4, 3, and 2. (Read more)

- Video Advertisement -

Related Post

Germany Reaffirms Commitment to Cambodia’s Infrastructure Development

In a significant milestone marking 32 years of diplomatic relations, Germany has played a pivotal role in enhancing Cambodia’s infrastructure, contributing to the development of over 2,000 kilometers of roadways. This achievement was highlighted during a recent meeting between His Excellency Chhay Rithsen, Cambodia’s Minister of Rural Development, and Mr. Gidon Windecker, a representative of […]

Government Proposes Enhancements to Phnom Penh-Sihanoukville Expressway Aesthetics and Safety

In a significant effort to enhance the visual appeal and safety of the Phnom Penh-Sihanoukville Expressway, the Concession Agreement Management Committee convened discussions on June 2, 2025, featuring representatives from the Ministry of Public Works and Transport, the Ministry of Economy and Finance, and various industry experts. The meeting focused on five key proposals aimed […]

National Road 7 Expansion Project Progress Report: 56% Complete

The expansion and upgrade of National Road 7, stretching from Skun Roundabout to Kizuna Bridge, has reached an impressive 56% completion, as announced by His Excellency Un Chanda, Governor of the Kampong Cham Provincial Government, during a recent Provincial Council meeting. The Governor provided a comprehensive overview of the project’s progress, highlighting notable advancements in […]

Twin Flyovers Near Completion at Phnom Penh-Kandal Border

  The construction of the Samdech Thipadei Hun Manet flyover, connecting Phnom Penh and Kandal province, has reached an impressive milestone with 85% of the project completed. The latest update comes as the twin flyovers advance toward the final stages of construction. A significant ceremony marking the connection of the bridge body was held on […]

Major Infrastructure Project Nears Completion in Siem Reap

A significant infrastructure development is underway in Siem Reap province, with a 15-kilometer road connecting National Road 6 to the Kampong Phluok tourist area now approximately 70% complete, according to an announcement from the Siem Reap administration. This vital roadway, which measures 8 meters in width, is part of a project initiated by Prime Minister […]

Japan’s JBIC Eyes Partnership for Major Infrastructure Development in Cambodia

The Japan Bank for International Cooperation (JBIC) has showcased a strong interest in collaborating on significant infrastructure projects in Cambodia. This development was announced following a meeting between Prime Minister Hun Manet and JBIC President and CEO Maeda Tadashi on May 28, 2025. During their discussions, President Maeda emphasized JBIC’s commitment to fostering partnerships with […]