Koh Pich-Koh Norea Bridge Nears Completion: Connection Set for 10 September with Milestone 92% Achieved

As Phnom Penh continues to mark impressive milestones in urban infrastructure, the much-anticipated Koh Pich-Koh Norea Bridge is poised to become a tangible symbol of connectivity. The cable-stayed concrete bridge, seamlessly linking Koh Pich and Koh Norea, is set to achieve a significant feat on 10 September 2023, with completion progress reaching an impressive 92%. This significant update was shared by HE Keut Chhe, Deputy Governor of Phnom Penh, on 31 August 2023.

Amidst this fervent anticipation, HE Khuong Sreng, Governor of Phnom Penh, will take the helm during the ceremonious connection of this innovative cable-stayed concrete bridge. The bridge is not merely a physical connection but a testament to the city’s vision of fostering seamless accessibility between its diverse locales.

The Koh Pich-Koh Norea Bridge, an ambitious project situated in Sangkat Niroth, Khan Chbar Ampov, Phnom Penh, bears testament to Cambodia’s resolute commitment to progressive infrastructure. With an investment of US$38 million, this bridge is the brainchild of the Overseas Cambodian Investment Company (OCIC), executed under the adept guidance of the Phnom Penh Capital Administration. (Read more)

The timely progress of the bridge’s construction aligns strategically with its scheduled completion in mid-November 2023. This auspicious timing underscores a concerted effort to enhance the city’s connectivity ahead of the Royal Water Festival, offering citizens and visitors an unprecedented experience of the city’s transformation.

As the final cables are meticulously secured and the last touches are applied, the Koh Pich-Koh Norea Bridge stands poised to be more than a physical link—it signifies Phnom Penh’s unwavering resolve to unite its vibrant communities and propel the city into a new era of accessible urban living.

- Video Advertisement -

Related Post

Electric Bus Revolution in Siem Reap: A Step Towards Sustainable Transport

In an exciting development for eco-friendly public transport, Cambodia, in partnership with the Green Development Institute (GGGI), has unveiled plans for an electric bus system in Siem Reap province. The announcement came during the final workshop of the electric bus public transport system study, where three strategic routes and 33 waiting stations were officially designated. […]

Progress Report: Siem Reap River Improvement Project Phase 2 Nears Completion

The Siem Reap River Improvement Project Phase 2 is making significant strides, with the project now completed by 97%. The Siem Reap Provincial Administration announced on August 21, 2025, via its official Facebook page that the project is on track for completion by July 1, 2025. The ongoing work focuses on restoring the river and […]

National Road 7 Expansion Project on Track for Early Completion

The ambitious project to expand and improve National Road 7, transforming it from a two-lane to a four-lane highway, is currently 43% complete and is expected to finish ahead of schedule. The 45.5-kilometre stretch of road runs from Vang Vong Moul Skun in Cheung Prey District to the base of the Kizuna Bridge in Kampong […]

India-Myanmar-Thailand Trilateral Highway Stalled Amid Conflict in Myanmar

The USD 114 billion India-Myanmar-Thailand Trilateral Highway, a crucial 1,360-kilometre infrastructure project designed to enhance ASEAN economic integration and strengthen India’s trade presence in Southeast Asia, faces major setbacks due to ongoing instability in Myanmar. Designed as a four-lane highway, the Trilateral Highway is part of India’s broader infrastructure vision, which aims to extend road […]

The Construction of Sewage System and Rainwater Pumping Station is Officially Ground Breaking in Kratie City

The construction of a vital sewerage system and rainwater pumping station, officially ground-breaking on 5th March in Kratie City, is backed by over USD 7 million in funding through the Asian Development Bank-supported Rabien 4 urban development project. H.E. Poo Manit, Deputy Director General of the Project at the Ministry of Public Works and Transport, […]

Mekong River Bridge in Kratie Province Approaching Completion

The long-awaited Mekong River Bridge, stretching 1,761 meters, is on the verge of completion, now standing at an impressive 89.84%. Local authorities anticipate the temporary opening to the public in September 2025, marking a significant milestone in the region’s infrastructure development. His Excellency Lim Sidenin, Secretary of State and Project Director, provided insights during a […]