US$100 million 11-Road Renovation Project in SHV 31% Complete

The US$100 million 11-road renovation project in Sihanoukville is now 31% complete, according to the Ministry of Public Works and Transport on 16 February.

HE Sun Chanthol said during the 2020 Work Progress Conference that the 11-road project is now 31.15% complete. Meanwhile, the restoration of five natural canals with a total length of 27.5 km is also 96.62% complete.

This 11-road project is an additional public works to the 34-road project which are set to open for public this upcoming April. (Read more)

HE Sun Chanthol also added that construction of the US$2 billion Phnom Penh-Sihanoukville expressway is also 31.19% complete. Meanwhile, another massive project, the 38-road infrastructure upgrade in Siem Reap is now 11.68% complete.

- Video Advertisement -

Related Post

Japan’s JBIC Eyes Partnership for Major Infrastructure Development in Cambodia

The Japan Bank for International Cooperation (JBIC) has showcased a strong interest in collaborating on significant infrastructure projects in Cambodia. This development was announced following a meeting between Prime Minister Hun Manet and JBIC President and CEO Maeda Tadashi on May 28, 2025. During their discussions, President Maeda emphasized JBIC’s commitment to fostering partnerships with […]

The Government Announces New Opening Date for Techo International Airport

In a significant new update for travelers and the aviation industry, the State Secretariat of Civil Aviation has announced a revised opening date for the much-anticipated Techo International Airport in Takhmao. Originally set to open on July 10, 2025, the grand opening is now scheduled for September 9, 2025, as indicated in a notice issued […]

National Road 10 Completed: Enhancing Regional Connectivity

The construction of National Road 10, stretching over 197.36 kilometers, has been officially completed, marking a significant milestone in the region’s infrastructure development. The road is now fully operational and has undergone a thorough inspection by a team of skilled technicians to ensure its longevity and adherence to technical standards. A detailed assessment was conducted […]

Singapore Resumes Construction of Changi Airport’s Largest Passenger Terminal After Pandemic Delay

In a significant milestone for Singapore’s aviation sector, the construction of Terminal 5 (T5) at Changi Airport has officially commenced following a two-year pause brought on by the COVID-19 pandemic. The groundbreaking ceremony, which took place on May 14, 2025, was graced by Prime Minister Lawrence Wong. Prime Minister Wong highlighted that the new terminal […]

Doun Tri Dam Construction 97% Completion

  The construction of the Doun Tri Dam in Battambang province is now 97% complete, with final completion expected by October 2025. This significant infrastructure project, located in Rukkakiri district, is being financed through concessional loans from the Republic of Korea. During a project progress review led by His Excellency Tho Jetha, Minister of Water […]

Irrigation System Project in Banteay Meanchey and Battambang is 75% Completed

  Banteay Meanchey and Battambang provinces are making strides in agricultural development as the irrigation system construction project reaches a significant milestone. As of May 7, 2025, the project is 75% complete, thanks to financing from the Korean Eximbank. During a progress review meeting led by His Excellency Minister Tho Jetha, Minister of Water Resources […]