12 Major Infrastructure Development Projects Progress Nationwide

Despite the COVID-19 crisis, Minister of Public Works and Transport HE Sun Chanthol has affirmed that all infrastructure development projects in Cambodia are running smoothly without any interruptions.

During a virtual meeting with the Infrastructure and Regional Integration Technical Working Group (IRITWG) on Thursday 19 August, the minister also provided a summary of progress on 12 major infrastructure development projects.

1) The Ministry has completed negotiations with a contractor on the Kratie-Kampong Thom Mekong River bridge project, with construction scheduled to begin by the end of 2021

2) MPWT already signed a construction agreement on the project to upgrade NR41, 31 and 33, from DBST to AC, while the construction is expected to begin soon.

3) Feasibility study of the 4th Phnom Penh ring road is still underway

4) Feasibility of study to build a new road connecting Kampong Chhnang and Kampong Thom province has been completed

5) MPWT in cooperation with a China Road and Bridge Corporation have completed the study of the new 72km road connecting Battambang to Siem Reap

6) The construction Phnom Penh-Sihanoukville Expressway has reached 65% and is scheduled to be completed in September 2022.

7) The Ministry is still studying the feasibility of the Phnom Penh-Bavet-Mokbai Expressway project in form of Build Operate Transfer (BOT)

8) Construction of the 34-road project in Sihanoukville has been completed.

9) The 38-road project Siem Reap is over 70% complete and is scheduled to be completed by the end of this year.

10) The Ministry is finalising the railway development strategy and will soon submit it for PM Hun Sen approval.

11) The project to expand the Sihanoukville port continues smoothly

12) MPWT is also planning to expand the capacity of several ports, including Kampot Port, Phnom Penh Autonomous Port, among other river ports to meet growing demand.

- Video Advertisement -

Related Post

A $117 Million Economic Lifeline: Prime Minister Hun Manet Inaugurates Newly Expanded National Road 7

The newly upgraded 4-lane highway connecting Skun and Kampong Cham town is projected to deliver a 15.27% economic return, slashing travel times and boosting agricultural trade… In a major boost to Cambodia’s internal logistics network, a vital 45.489-kilometer section of National Road 7 connecting the Skun roundabout to the Kizuna Bridge roundabout in Kampong Cham […]

Maritime Geopolitical Rivalry Intensifies as Vietnam Accelerates $4 Billion Deep Sea Port Project in the Far South

The massive infrastructure development on Hon Khoai Island serves as both an economic gateway for the Mekong Delta and a strategic maritime shield amid shifting regional dynamics Ho Chi Minh City: The geopolitical and trade landscape of Southeast Asia is entering a highly competitive phase as nations across the region race to build strategic advantages. […]

Field Assessments Underway for Kandal Province New Strategic Bridge

A joint delegation evaluates four potential sites for the Koh Khsach Tonlea crossing to enhance rural connectivity and market access In a significant step forward for Cambodia’s infrastructure development, a multi-institutional technical team has launched a comprehensive field survey to determine the optimal location for the upcoming Koh Khsach Tonlea Bridge project in Kandal Province. […]

Cambodia Completes Major Expansion of National Road 7 Connecting Skun and Kampong Cham

The $117 million infrastructure upgrade backed by China is set for an official inauguration by Prime Minister Hun Manet in July… The extensive upgrade of National Road 7, stretching over 45 kilometers to connect the hub of Skun with Kampong Cham town, has officially reached 100% completion. To mark this infrastructural milestone, a formal handover […]

Cambodia to Upgrade National Road 4 Section in Chbar Mon to Drive Regional Economic Growth

The Kampong Speu Provincial Administration recently announced a comprehensive infrastructure initiative aimed at upgrading the aesthetics and functionality of a key section of National Road 4 within Chbar Mon City. The project is strategically designed to transform the province into a vital economic and commercial center for the region. This development plan was detailed in […]

Bassac Riverbank Stabilization Project in Kandal Reaches 60% Completion

The ongoing infrastructure initiative to reinforce the Bassac riverbank in Sampov Poun City, Kandal Province, has achieved a significant milestone, with construction teams completing approximately 60% of the designated works. Local authorities and engineering crews remain heavily committed to accelerating the remaining phases to ensure the project concludes entirely on schedule. During a recent field […]