Construction of 15ha ADB-funded standardized landfill in Pursat 98% complete

The construction of the standard solid waste management site in Pursat City is over 98% complete and is scheduled to be operational soon, according to the site by Pursat Governor HE Cheav Tay on Tuesday 28 December.

Among all construction works, the two main landfills are 100% complete, the administration building 100%, the wastewater treatment tank 100%, smell treatment plant 81%, entrance gate 50%, and garbage truck weighing station 44%.

Located in Tuol Makak village, Sangkat Roleap, Pursat city, the landfill project is funded by a concessional loan from the Asian Development Bank (ADB) of approximately US$1.6 million.

This project is being built by Ung Sim Sea Construction Company on an area of more than 15 hectares, which the construction started in April 2020.

During the inspection, HE Cheav Tay also urged the construction company to ensure the construction quality, while also speeding up progress so that it can be completed as scheduled.

- Video Advertisement -

Related Post

Final Section of Cambodia’s National Road 5 Reaches Major Construction Milestone

Achieving over 63 percent completion, the vital Serei Sophorn to Poipet corridor paves the way for seamless international trade and regional connectivity by 2027 The ambitious transformation of Cambodia’s transport network is rapidly nearing its final triumph as the restoration and quality upgrade of National Road 5 enters its last leg. By the end of […]

The Bassac River Bridge Nears Spectacular Completion to Transform Phnom Penh Infrastructure

Phnom Penh is rapidly advancing toward an era of unprecedented urban connectivity as the highly anticipated Bassac River Bridge construction project charges toward its final phases. As of early July 2026, this iconic twin concrete bridge connecting Chak Angre Krom and Prek Pra has achieved a spectacular 79% completion rate. This major milestone was underscored […]

A $117 Million Economic Lifeline: Prime Minister Hun Manet Inaugurates Newly Expanded National Road 7

The newly upgraded 4-lane highway connecting Skun and Kampong Cham town is projected to deliver a 15.27% economic return, slashing travel times and boosting agricultural trade… In a major boost to Cambodia’s internal logistics network, a vital 45.489-kilometer section of National Road 7 connecting the Skun roundabout to the Kizuna Bridge roundabout in Kampong Cham […]

Maritime Geopolitical Rivalry Intensifies as Vietnam Accelerates $4 Billion Deep Sea Port Project in the Far South

The massive infrastructure development on Hon Khoai Island serves as both an economic gateway for the Mekong Delta and a strategic maritime shield amid shifting regional dynamics Ho Chi Minh City: The geopolitical and trade landscape of Southeast Asia is entering a highly competitive phase as nations across the region race to build strategic advantages. […]

Field Assessments Underway for Kandal Province New Strategic Bridge

A joint delegation evaluates four potential sites for the Koh Khsach Tonlea crossing to enhance rural connectivity and market access In a significant step forward for Cambodia’s infrastructure development, a multi-institutional technical team has launched a comprehensive field survey to determine the optimal location for the upcoming Koh Khsach Tonlea Bridge project in Kandal Province. […]

Cambodia Completes Major Expansion of National Road 7 Connecting Skun and Kampong Cham

The $117 million infrastructure upgrade backed by China is set for an official inauguration by Prime Minister Hun Manet in July… The extensive upgrade of National Road 7, stretching over 45 kilometers to connect the hub of Skun with Kampong Cham town, has officially reached 100% completion. To mark this infrastructural milestone, a formal handover […]