Construction of Stueng Trang-Krouch Chmar Bridge finished by December

The Cambodia-China Friendship Bridge (CRC) is 84% complete, according to HE Sun Chanthol, Minister of Public Works and Transport at a press conference on “Progress and Continuing Direction of Ministry of Public Works and Transport organised by the government spokesperson’s office at the Council of Ministers on 21 February 2020.

Linking Stung Trang (Kampong Cham) to Krouch Chhmar (Tbong Khmum), the construction of this bridge began on 9 February 2018 and is now 84% complete. The bridge body is expected to be finished by the end of December, while additional works such as asphalt concrete flooring as well as installing signs and poles will be completed by 2021.

Prime Minister Samdech Hun Sen said at the groundbreaking ceremony that the project is the third bridge across the Mekong River that was built in Cambodia with the help of China. Each bridge represents the strong friendship between China and Cambodia.

The bridge shows solid ties between Cambodia and China, and also results in huge economic benefits in terms of logistics. This bridge can be a shortcut for exporting and importing goods between Trapeang Tlung, Tbong Khmum province and Tan Bin, Tay Ninh province, Vietnam.

- Video Advertisement -

Related Post

Cambodia Nears Completion of Strategic Border Ring Road in Northeastern Provinces

Funded by the Border Infrastructure Fund, the infrastructure project in Mondulkiri and Ratanakiri achieves over 95% of its construction targets Cambodia’s ambitious infrastructure initiative to establish a continuous border ring road is nearing full completion, with construction teams successfully executing the vast majority of planned developments in Mondulkiri and Ratanakiri provinces. From the commencement of […]

Construction of Bassac River Bridge Linking Chak Angre Krom and Prek Pra Reaches 73% Completion

The construction of the highly anticipated bridge across the Bassac River, connecting Chak Angre Krom to Prek Pra, has achieved a major milestone, reaching 73% completion by the end of May 2026. According to the inspection team on 01 June 2026, led by HE Soung Heng, Secretary of State and Project Director, to monitor the […]

Bakheng Water Treatment Plant Expansion Crosses Major Threshold to Secure Capital Clean Water Access

Phase Three Progress Surpasses Seventy % Mark as Cambodia Broadens Utility Infrastructure to Support Rapid Economic Growth The ongoing construction of the Bakheng Water Treatment Plant Phase Three has achieved a significant milestone, with the project now certified as more than 70 % complete. This infrastructure expansion is poised to critically enhance the water distribution […]

Takhmao City Wastewater Infrastructure Project Reaches One-Third Completion Milestone

The construction of the wastewater treatment system in Takhmao City, Kandal Province, has reached a significant milestone, achieving an overall progress of 33 percent as of the end of April 2026. This advancement was confirmed during a site visit on May 7, 2026, led by His Excellency Ros Vanna, Secretary of State of the Ministry […]

Cambodia and Japan Sign Consultancy Agreement for Koh Ksach Tonlea Bridge Project in Kandal Province

The Ministry of Public Works and Transport and the Japanese consortium CHODAI Co., LTD have formally signed a consulting services agreement for the Koh Ksach Tonlea Bridge construction project in Kandal Province. The signing ceremony took place on May 8, 2026, under the high presidency of His Excellency Peng Ponea, Minister of Public Works and […]

Japan Pledges $47 Million to Strengthen Flood Resilience and Wastewater Infrastructure in Phnom Penh

Japan has officially extended a $47 million credit facility to support a comprehensive flood protection and wastewater drainage development project in the Cambodian capital. This strategic funding follows a formal exchange of notes between the Royal Government of Cambodia and the government of Japan on April 23, 2026. The announcement was formalized during a recent […]