Construction of Two Major Bridges Connecting to Koh Norea Over 14% Complete

Construction of two major bridge projects, one of which connects Koh Pich city to Koh Norea and another connecting Koh Norea to NR1, on average are over 14.7% complete as of September, according to Koh Norea Project Manager Men Poly.

Mr Poly told Construction & Property Magazine on Wednesday that the bridge connecting Koh Norea to NR1 is only 2.5% complete, while the other connecting Koh Pich city to Koh Norea is 27% complete.

Being developed by the Overseas Cambodia Investment Corporation (OCIC), ground was broken on the two bridges in October last year, marking a new stage of the US$2.5-billion satellite city.

The first bridge connecting NR1 to Korea is a rainbow-shaped concrete bridge that is 16 metres long and 21 metres wide while the construction is expected to cost US$1.6 million.

Meanwhile, the second bridge connecting Koh Pich to Koh Norea is expected to cost US$38 million. It is 824 metres long and 24.5 metres wide and has two 60-metre-high cable-stayed pillars with Khmer carvings. The bridge has four main lanes and two motorbike lanes of 3.25 metres and 1.24 metres wide each.

These two bridges are part of the OCIC’s mega project of turning Koh Norea into a new satellite city.

To date, the construction of overall infrastructure for Koh Norea is over 48% complete. (Read more)

- Video Advertisement -

Related Post

Final Section of Cambodia’s National Road 5 Reaches Major Construction Milestone

Achieving over 63 percent completion, the vital Serei Sophorn to Poipet corridor paves the way for seamless international trade and regional connectivity by 2027 The ambitious transformation of Cambodia’s transport network is rapidly nearing its final triumph as the restoration and quality upgrade of National Road 5 enters its last leg. By the end of […]

The Bassac River Bridge Nears Spectacular Completion to Transform Phnom Penh Infrastructure

Phnom Penh is rapidly advancing toward an era of unprecedented urban connectivity as the highly anticipated Bassac River Bridge construction project charges toward its final phases. As of early July 2026, this iconic twin concrete bridge connecting Chak Angre Krom and Prek Pra has achieved a spectacular 79% completion rate. This major milestone was underscored […]

A $117 Million Economic Lifeline: Prime Minister Hun Manet Inaugurates Newly Expanded National Road 7

The newly upgraded 4-lane highway connecting Skun and Kampong Cham town is projected to deliver a 15.27% economic return, slashing travel times and boosting agricultural trade… In a major boost to Cambodia’s internal logistics network, a vital 45.489-kilometer section of National Road 7 connecting the Skun roundabout to the Kizuna Bridge roundabout in Kampong Cham […]

Maritime Geopolitical Rivalry Intensifies as Vietnam Accelerates $4 Billion Deep Sea Port Project in the Far South

The massive infrastructure development on Hon Khoai Island serves as both an economic gateway for the Mekong Delta and a strategic maritime shield amid shifting regional dynamics Ho Chi Minh City: The geopolitical and trade landscape of Southeast Asia is entering a highly competitive phase as nations across the region race to build strategic advantages. […]

Field Assessments Underway for Kandal Province New Strategic Bridge

A joint delegation evaluates four potential sites for the Koh Khsach Tonlea crossing to enhance rural connectivity and market access In a significant step forward for Cambodia’s infrastructure development, a multi-institutional technical team has launched a comprehensive field survey to determine the optimal location for the upcoming Koh Khsach Tonlea Bridge project in Kandal Province. […]

Cambodia Completes Major Expansion of National Road 7 Connecting Skun and Kampong Cham

The $117 million infrastructure upgrade backed by China is set for an official inauguration by Prime Minister Hun Manet in July… The extensive upgrade of National Road 7, stretching over 45 kilometers to connect the hub of Skun with Kampong Cham town, has officially reached 100% completion. To mark this infrastructural milestone, a formal handover […]