Bridge Construction Across Bassac River Surpasses Milestone Ahead of Schedule

The ambitious project to construct a bridge spanning the Bassac River, linking Chak Angre Krom to Prek Pra, has surpassed expectations by achieving a remarkable 7.5% progress in just two months, surpassing the planned timeline by 0.6%.

This significant milestone, achieved ahead of schedule, underscores the swift and efficient progress of the construction efforts since its commencement on 19 February as highlighted in an update shared on the official Facebook page of the Ministry of Public Works and Transport on 19 April 2024.

The construction progress to date showcases commendable achievements, with the completion of 24 out of the planned nine pillars, with concrete work reaching 100% completion and ongoing installation of templates. Additionally, significant strides have been made with the 10th pillar of the 9th pillar, with 12 pillars already in place and four trees successfully drilled.

The bridge, boasting a total length of 1,650 metres, comprises a bridge length of 845.70 metres and a road width of 27 metres, along with a road connecting bridge length of 804.30 metres.

Constructed by Shanghai Construction Company, under the project consultancy of Guangzhou Wan An, this monumental infrastructure endeavour has been made possible through a US$60.2 million investment concessional loan from the Chinese government, in collaboration with Cambodian government. (Read more)

- Video Advertisement -

Related Post

Darasakor International Airport Opens Its Doors in Koh Kong

Koh Kong Province has marked a significant milestone with the grand opening of Darasakor International Airport on December 26, 2024. This $200 million investment, overseen by the Chinese company Union Development Group, represents a major advancement in Cambodia’s aviation sector and is set to transform travel in the region. The airport officially welcomed its first […]

The new road connecting NR No. 4 to Bokor Mountain has completed 7 km of concrete pouring work

The construction of a new 61-kilometre road connecting National Road No. 4 to Bokor Mountain is currently underway, with 7 kilometres of concrete pouring completed as of December 19, 2024. This update was posted on the official Facebook page of Sokha Real Estate on the afternoon of that date. According to the project plan developed […]

NR 41 Completion Marks Milestone in Cambodian Transportation

NR 41, a vital addition to Cambodia’s infrastructure, has officially been completed with a total investment exceeding $67 million. Stretching over 95 kilometres, the road links NR 4 in Kandal to NR 3 in Kampot, dramatically enhancing regional connectivity and bolstering travel and trade. The announcement came following a detailed inspection led by HE Sui […]

Funan Techo Canal Completes 142 demarcation points, Sets Stage for Transformative Infrastructure Shortly

In a landmark achievement for Cambodia’s infrastructure development, the inter-ministerial technical working group has successfully completed the boundary posting process for the first 21 kilometres of the Funan Techo Canal. This initial section, stretching from Prek Takeo to Prek Po, has reached 100% completion, with 142 demarcation points now established along the route. This milestone […]

The Gov’t Temporarily Opens Morodok Techo Flyover’s First Floor Ahead of Khmer New Year 2025

To enhance urban mobility and alleviate traffic congestion in Phnom Penh, the Cambodian government has announced the temporary opening of the first floor of the highly anticipated Morodok Techo Flyover ahead of the Khmer New Year celebrations 2025. This development comes as part of efforts to facilitate smoother travel during the bustling Khmer New Year […]

Cambodia Completes 271 Rural Road Projects in 2024, Enhancing Accessibility Across Remote Areas

The Cambodian government has announced the successful completion of 271 rural road projects in 2024, significantly boosting transportation accessibility for remote communities. The Ministry of Rural Development presented these achievements during a year-end meeting on 9 December 2024, highlighting the construction and improvement of approximately 940.71 kilometres of double-paved roads and outlining strategic plans for […]