Bridge Construction Across Bassac River Surpasses Milestone Ahead of Schedule

The ambitious project to construct a bridge spanning the Bassac River, linking Chak Angre Krom to Prek Pra, has surpassed expectations by achieving a remarkable 7.5% progress in just two months, surpassing the planned timeline by 0.6%.

This significant milestone, achieved ahead of schedule, underscores the swift and efficient progress of the construction efforts since its commencement on 19 February as highlighted in an update shared on the official Facebook page of the Ministry of Public Works and Transport on 19 April 2024.

The construction progress to date showcases commendable achievements, with the completion of 24 out of the planned nine pillars, with concrete work reaching 100% completion and ongoing installation of templates. Additionally, significant strides have been made with the 10th pillar of the 9th pillar, with 12 pillars already in place and four trees successfully drilled.

The bridge, boasting a total length of 1,650 metres, comprises a bridge length of 845.70 metres and a road width of 27 metres, along with a road connecting bridge length of 804.30 metres.

Constructed by Shanghai Construction Company, under the project consultancy of Guangzhou Wan An, this monumental infrastructure endeavour has been made possible through a US$60.2 million investment concessional loan from the Chinese government, in collaboration with Cambodian government. (Read more)

- Video Advertisement -

Related Post

National Road 7 Expansion Project Nears Completion as Vital Economic Link Reaches 90% Finish

Accelerated construction on the Skun to Kampong Cham corridor aims for early delivery to boost regional trade and transport efficiency The expansion and upgrade of National Road 7, a critical infrastructure project connecting the Skun area to Kampong Cham city, has reached nearly 90% completion as of March 2026. This significant milestone was highlighted by […]

Cambodia Road Network Expands to Over 20,000 Kilometers in 2025

Strategic infrastructure development adds 426 kilometers to the national network to boost logistics and economic growth The total length of developed roads in Cambodia reached 20,733.91 kilometers by the end of 2025, marking a notable increase of approximately 426.32 kilometers compared to the previous year. This data was highlighted in the 2025 Annual Progress Report […]

Cambodia and Laos to Fast-Track Cross-Border Connectivity with New Ratanakiri-Attapeu Road Link

Joint inspection team to finalize construction zones this February to unlock new trade and economic opportunities Cambodia and Laos have reached a pivotal agreement to conduct a joint technical inspection aimed at defining the specific zones for a new road project connecting Ratanakiri province in Cambodia to Attapeu province in Laos. This initiative is a […]

Pursat Provincial Authorities Inaugurate New Bridge and Kick Off Construction of Nine Rural Roads

In a significant boost to local infrastructure, the Royal Government of Cambodia officially inaugurated a new 75-meter concrete bridge and announced the construction of nine additional rural roads in Pursat Province. The ceremony presided over by His Excellency Chhay Rithsen, Minister of Rural Development, marked a milestone for the community. The newly inaugurated bridge, connecting […]

Bassac River Bridge in Chak Angre Krom–Prek Pra Reaches 51% Completion

As of October 28, 2025, construction of the Bassac River Crossing Bridge connecting Chak Angre Krom to Prek Pra has reached 51% completion, according to the Ministry of Public Works and Transport (MPWT). A recent on-site inspection led by His Excellency Suong Heng, Secretary of State and Project Director, revealed steady progress across key construction […]

National Road 23 Fully Completed, Boosting Connectivity and Regional Growth

The Ministry of Public Works and Transport has officially announced the full completion of the National Road 23 (NR23) upgrade, marking a significant achievement in Cambodia’s ongoing infrastructure development. The announcement was made on October 24, 2025, following the completion of a 19.8-kilometer section designed to improve transportation efficiency and accessibility for local residents. The […]