New Bassac River Crossing Surpasses 68% Completion as Project Moves Ahead of Schedule

The construction of the Bassac River Bridge connecting Chak Angre Krom and Prek Pra has entered a high-velocity phase, with total progress reaching approximately 68% as of April 20, 2026. According to Phon Rim, spokesperson for the Ministry of Public Works and Transport, the strategic infrastructure project is currently 6% ahead of its original development schedule, signaling a potential early boost for capital connectivity.

The bridge features a total length of 1,650 meters, anchored by a main river crossing of 845.70 meters and a roadway width of 27 meters. Complementing the main structure are approach roads measuring 804.30 meters in length with a standard 20-meter width, designed to integrate seamlessly into the surrounding urban landscape.

Detailed technical updates reveal that the project’s critical foundational works have achieved 100% completion. Significant progress is also evident in the substructure, which is 89% finished, while the superstructure has reached 28% completion. In terms of specific structural components, 132 out of 180 pre-cast T-beams and 156 out of 180 cast-in-place T-beams have already been finalized.

Beyond the main bridge structure, associated works are advancing across multiple fronts. The road network construction is 44.4% complete, while connection sections have reached the halfway mark at 50%, and ramp construction stands at 42%. These figures reflect a coordinated effort to ensure the entire facility is ready for its anticipated full completion by the end of 2027.

Once operational, the Chak Angre Krom-Prek Pra bridge is expected to be a game-changer for southern Phnom Penh, drastically reducing traffic congestion on the existing Preah Monivong Bridge. By providing a direct link between National Road 1 in Chbar Ampov district and the developing corridors leading to the Techo International Airport in Ta Khmau, the crossing will strengthen both economic and social ties within the capital region. This project, which broke ground in February 2024, remains a cornerstone of the government’s vision to enhance transportation and logistics efficiency across the Kingdom. (read more)

- Video Advertisement -

Related Post

Japan-Funded 20,000-Hectare Southwest Phnom Penh Irrigation Scheme Nears 99% Completion

Inspected by Water Resources Minister Thor Chetha, the major JICA infrastructure project across Kampong Speu, Kandal, and Takeo promises to boost rice yields for nearly 8,000 farming families Agricultural productivity and flood management southwest of Cambodia’s capital are set for a major transformation as the Rehabilitation and Improvement of Irrigation and Drainage Systems Project in […]

Bassac and Prek Koy Riverbank Protection Projects Achieve 100% Completion Across Kandal and Kampong Cham

Cambodia’s water infrastructure development achieved a key milestone as two major riverbank protection projects along the Bassac River and Prek Koy stream reached 100% completion across Kandal and Kampong Cham provinces. An inter-ministerial working group led by HE Sot Rasmei, Secretary of State and Chairman of the Procurement Committee at the Ministry of Water Resources […]

Jinding Air Liquefaction Breaks Ground on $10 Million Industrial Gas Plant in Kampong Speu

Cambodia’s industrial supply chain achieved a major milestone with the official groundbreaking of the nation’s first large-scale industrial gas production facility in Kampong Speu province. Valued at over $10 million, the flagship project developed by Jinding Air Liquefaction (Cambodia) Co., Ltd. officially commenced construction on July 2, 2026, during a ceremony presided over by Kampong […]

Chip Mong Breaks Ground on $250 Million Food and Beverage Production Complex in Phnom Penh

Domestic manufacturing in Cambodia achieved a major milestone as local conglomerate Chip Mong officially broke ground on a state-of-the-art food and beverage production facility valued at over $250 million. The groundbreaking ceremony held on August 1, 2026, was presided over by Samdech Men Sam An, Privy Councillor to His Majesty the King, in Khan Dangkao, […]

Final Section of Cambodia’s National Road 5 Reaches Major Construction Milestone

Achieving over 63 percent completion, the vital Serei Sophorn to Poipet corridor paves the way for seamless international trade and regional connectivity by 2027 The ambitious transformation of Cambodia’s transport network is rapidly nearing its final triumph as the restoration and quality upgrade of National Road 5 enters its last leg. By the end of […]

The Bassac River Bridge Nears Spectacular Completion to Transform Phnom Penh Infrastructure

Phnom Penh is rapidly advancing toward an era of unprecedented urban connectivity as the highly anticipated Bassac River Bridge construction project charges toward its final phases. As of early July 2026, this iconic twin concrete bridge connecting Chak Angre Krom and Prek Pra has achieved a spectacular 79% completion rate. This major milestone was underscored […]