New Bassac River Crossing Surpasses 68% Completion as Project Moves Ahead of Schedule

The construction of the Bassac River Bridge connecting Chak Angre Krom and Prek Pra has entered a high-velocity phase, with total progress reaching approximately 68% as of April 20, 2026. According to Phon Rim, spokesperson for the Ministry of Public Works and Transport, the strategic infrastructure project is currently 6% ahead of its original development schedule, signaling a potential early boost for capital connectivity.

The bridge features a total length of 1,650 meters, anchored by a main river crossing of 845.70 meters and a roadway width of 27 meters. Complementing the main structure are approach roads measuring 804.30 meters in length with a standard 20-meter width, designed to integrate seamlessly into the surrounding urban landscape.

Detailed technical updates reveal that the project’s critical foundational works have achieved 100% completion. Significant progress is also evident in the substructure, which is 89% finished, while the superstructure has reached 28% completion. In terms of specific structural components, 132 out of 180 pre-cast T-beams and 156 out of 180 cast-in-place T-beams have already been finalized.

Beyond the main bridge structure, associated works are advancing across multiple fronts. The road network construction is 44.4% complete, while connection sections have reached the halfway mark at 50%, and ramp construction stands at 42%. These figures reflect a coordinated effort to ensure the entire facility is ready for its anticipated full completion by the end of 2027.

Once operational, the Chak Angre Krom-Prek Pra bridge is expected to be a game-changer for southern Phnom Penh, drastically reducing traffic congestion on the existing Preah Monivong Bridge. By providing a direct link between National Road 1 in Chbar Ampov district and the developing corridors leading to the Techo International Airport in Ta Khmau, the crossing will strengthen both economic and social ties within the capital region. This project, which broke ground in February 2024, remains a cornerstone of the government’s vision to enhance transportation and logistics efficiency across the Kingdom. (read more)

- Video Advertisement -

Related Post

Final Section of Cambodia’s National Road 5 Reaches Major Construction Milestone

Achieving over 63 percent completion, the vital Serei Sophorn to Poipet corridor paves the way for seamless international trade and regional connectivity by 2027 The ambitious transformation of Cambodia’s transport network is rapidly nearing its final triumph as the restoration and quality upgrade of National Road 5 enters its last leg. By the end of […]

The Bassac River Bridge Nears Spectacular Completion to Transform Phnom Penh Infrastructure

Phnom Penh is rapidly advancing toward an era of unprecedented urban connectivity as the highly anticipated Bassac River Bridge construction project charges toward its final phases. As of early July 2026, this iconic twin concrete bridge connecting Chak Angre Krom and Prek Pra has achieved a spectacular 79% completion rate. This major milestone was underscored […]

A $117 Million Economic Lifeline: Prime Minister Hun Manet Inaugurates Newly Expanded National Road 7

The newly upgraded 4-lane highway connecting Skun and Kampong Cham town is projected to deliver a 15.27% economic return, slashing travel times and boosting agricultural trade… In a major boost to Cambodia’s internal logistics network, a vital 45.489-kilometer section of National Road 7 connecting the Skun roundabout to the Kizuna Bridge roundabout in Kampong Cham […]

Maritime Geopolitical Rivalry Intensifies as Vietnam Accelerates $4 Billion Deep Sea Port Project in the Far South

The massive infrastructure development on Hon Khoai Island serves as both an economic gateway for the Mekong Delta and a strategic maritime shield amid shifting regional dynamics Ho Chi Minh City: The geopolitical and trade landscape of Southeast Asia is entering a highly competitive phase as nations across the region race to build strategic advantages. […]

Field Assessments Underway for Kandal Province New Strategic Bridge

A joint delegation evaluates four potential sites for the Koh Khsach Tonlea crossing to enhance rural connectivity and market access In a significant step forward for Cambodia’s infrastructure development, a multi-institutional technical team has launched a comprehensive field survey to determine the optimal location for the upcoming Koh Khsach Tonlea Bridge project in Kandal Province. […]

Cambodia Completes Major Expansion of National Road 7 Connecting Skun and Kampong Cham

The $117 million infrastructure upgrade backed by China is set for an official inauguration by Prime Minister Hun Manet in July… The extensive upgrade of National Road 7, stretching over 45 kilometers to connect the hub of Skun with Kampong Cham town, has officially reached 100% completion. To mark this infrastructural milestone, a formal handover […]