New Bassac River Crossing Surpasses 68% Completion as Project Moves Ahead of Schedule

The construction of the Bassac River Bridge connecting Chak Angre Krom and Prek Pra has entered a high-velocity phase, with total progress reaching approximately 68% as of April 20, 2026. According to Phon Rim, spokesperson for the Ministry of Public Works and Transport, the strategic infrastructure project is currently 6% ahead of its original development schedule, signaling a potential early boost for capital connectivity.

The bridge features a total length of 1,650 meters, anchored by a main river crossing of 845.70 meters and a roadway width of 27 meters. Complementing the main structure are approach roads measuring 804.30 meters in length with a standard 20-meter width, designed to integrate seamlessly into the surrounding urban landscape.

Detailed technical updates reveal that the project’s critical foundational works have achieved 100% completion. Significant progress is also evident in the substructure, which is 89% finished, while the superstructure has reached 28% completion. In terms of specific structural components, 132 out of 180 pre-cast T-beams and 156 out of 180 cast-in-place T-beams have already been finalized.

Beyond the main bridge structure, associated works are advancing across multiple fronts. The road network construction is 44.4% complete, while connection sections have reached the halfway mark at 50%, and ramp construction stands at 42%. These figures reflect a coordinated effort to ensure the entire facility is ready for its anticipated full completion by the end of 2027.

Once operational, the Chak Angre Krom-Prek Pra bridge is expected to be a game-changer for southern Phnom Penh, drastically reducing traffic congestion on the existing Preah Monivong Bridge. By providing a direct link between National Road 1 in Chbar Ampov district and the developing corridors leading to the Techo International Airport in Ta Khmau, the crossing will strengthen both economic and social ties within the capital region. This project, which broke ground in February 2024, remains a cornerstone of the government’s vision to enhance transportation and logistics efficiency across the Kingdom. (read more)

- Video Advertisement -

Related Post

Bassac Riverbank Stabilization Project in Kandal Reaches 60% Completion

The ongoing infrastructure initiative to reinforce the Bassac riverbank in Sampov Poun City, Kandal Province, has achieved a significant milestone, with construction teams completing approximately 60% of the designated works. Local authorities and engineering crews remain heavily committed to accelerating the remaining phases to ensure the project concludes entirely on schedule. During a recent field […]

Cambodia and Vietnam Partner to Build Major Drug Rehabilitation Center in Svay Rieng

Cambodia and Vietnam are joining forces to establish an expansive National Drug Treatment and Rehabilitation Center in Svay Rieng Province. The planned facility will cover more than fifty-three hectares of land, marking a significant step forward in bilateral efforts to address substance dependency and long-term recovery. The project advanced further following a strategic meeting on […]

Cambodia Nears Completion of Strategic Border Ring Road in Northeastern Provinces

Funded by the Border Infrastructure Fund, the infrastructure project in Mondulkiri and Ratanakiri achieves over 95% of its construction targets Cambodia’s ambitious infrastructure initiative to establish a continuous border ring road is nearing full completion, with construction teams successfully executing the vast majority of planned developments in Mondulkiri and Ratanakiri provinces. From the commencement of […]

Construction of Bassac River Bridge Linking Chak Angre Krom and Prek Pra Reaches 73% Completion

The construction of the highly anticipated bridge across the Bassac River, connecting Chak Angre Krom to Prek Pra, has achieved a major milestone, reaching 73% completion by the end of May 2026. According to the inspection team on 01 June 2026, led by HE Soung Heng, Secretary of State and Project Director, to monitor the […]

Bakheng Water Treatment Plant Expansion Crosses Major Threshold to Secure Capital Clean Water Access

Phase Three Progress Surpasses Seventy % Mark as Cambodia Broadens Utility Infrastructure to Support Rapid Economic Growth The ongoing construction of the Bakheng Water Treatment Plant Phase Three has achieved a significant milestone, with the project now certified as more than 70 % complete. This infrastructure expansion is poised to critically enhance the water distribution […]

Takhmao City Wastewater Infrastructure Project Reaches One-Third Completion Milestone

The construction of the wastewater treatment system in Takhmao City, Kandal Province, has reached a significant milestone, achieving an overall progress of 33 percent as of the end of April 2026. This advancement was confirmed during a site visit on May 7, 2026, led by His Excellency Ros Vanna, Secretary of State of the Ministry […]