Progress Report on Romchek Irrigation System in Prey Veng Province

Significant strides have been made in the development of the Romchek irrigation system, which is now nearly 20% complete and poised to enhance agricultural productivity across the region. This comprehensive irrigation initiative is designed to serve a total area of nearly 2,000 hectares, ensuring both wet and dry rice fields receive the necessary water supply.

During a recent project inspection on March 23, 2025, led by Mr. Phang Vy, Director of the Department of Agricultural Irrigation at the Ministry of Water Resources and Meteorology, technical experts assessed the progress of the Romchek Canal irrigation system. Mr. Vy highlighted that the system will effectively irrigate approximately 1,200 hectares of wet rice and nearly 500 hectares of dry rice, as well as a variety of mixed crops.

The ongoing construction and maintenance of the Romchek Canal involve crucial repairs, including the restoration of a 3,200-meter-long main canal, the renovation of 13 existing structures, and the construction of two new art structures to facilitate optimal water flow.

Mr. Phang Vy emphasized the importance of collaboration among all stakeholders to ensure the long-term quality and sustainability of the irrigation system. This cooperative effort is vital for maximizing agricultural output and supporting local farmers.

In related news, the Ministry of Water Resources reports that Cambodia currently operates 2,352 irrigation systems, comprising 56 large-scale, 1,166 medium-scale, and 1,122 small-scale systems, along with eight large-scale reservoirs. The total irrigation capacity across the country has increased significantly, now standing at an impressive 1,969,843 hectares. (Read more)

As the Romchek irrigation system progresses, it promises to be a key asset for the agricultural landscape of Prey Veng, paving the way for increased crop yields and improved livelihoods for farmers in the region.

- Video Advertisement -

Related Post

National Road 48 Rehabilitation Project Nears Completion

In a significant development for regional connectivity, the rehabilitation of National Road 48, which spans 148 kilometers from Sre Ambel to Koh Kong province, is now 94.30% complete. The ambitious project aims to enhance transportation, logistics, and tourism along this vital economic corridor. The progress was confirmed during a recent inspection led by His Excellency […]

Border Ring Road Construction Progress Approaches 40% Milestone

The construction progress of the highly anticipated border ring road has reached nearly 40%, marking a significant step forward for the project. Currently, approximately 39.92% of the total construction plan has been completed, as reported in a press release today. The initiative, funded by the Border Infrastructure Fund (BIF), aims to enhance connectivity along the […]

Construction Progress of Phnom Penh’s Drainage System Nears Completion

The ambitious project to build a comprehensive drainage system in western Phnom Penh is now 88% complete, with final touches expected to be finalized by July 2025. During a recent review, Ms. Koy Sodany, Permanent Secretary of State at the Ministry of Public Works and Transport and the project leader, confirmed the significant progress. The […]

Electric Bus Revolution in Siem Reap: A Step Towards Sustainable Transport

In an exciting development for eco-friendly public transport, Cambodia, in partnership with the Green Development Institute (GGGI), has unveiled plans for an electric bus system in Siem Reap province. The announcement came during the final workshop of the electric bus public transport system study, where three strategic routes and 33 waiting stations were officially designated. […]

Progress Report: Siem Reap River Improvement Project Phase 2 Nears Completion

The Siem Reap River Improvement Project Phase 2 is making significant strides, with the project now completed by 97%. The Siem Reap Provincial Administration announced on August 21, 2025, via its official Facebook page that the project is on track for completion by July 1, 2025. The ongoing work focuses on restoring the river and […]

National Road 7 Expansion Project on Track for Early Completion

The ambitious project to expand and improve National Road 7, transforming it from a two-lane to a four-lane highway, is currently 43% complete and is expected to finish ahead of schedule. The 45.5-kilometre stretch of road runs from Vang Vong Moul Skun in Cheung Prey District to the base of the Kizuna Bridge in Kampong […]