Siem Reap 38-Road Renovation Project 14% Complete

As of 12 January, the 38-road renovation project in Siem Reap is 14.27% completed and still expected to finish as scheduled by the end of this year, according to the Ministry of Public Works and Transports (MPWT).

The progress was revealed during a meeting between Deputy Prime Minister Tea Banh, other relevant ministers and officials on 13 January.

With ground broken on 30 November last year, this massive renovation is considered a big step forward for this world-class tourism destination toward its goal to attract even more tourists after the COVID-19 pandemic ends.

With a total length of 108km and estimated to consume a total budget of US$140 million, this project stretches across 12 districts of Siem Reap city and a part of Prasat Bakong and the 38 roads will be well-connected with other main road systems to ease traffic congestion and reduce accidents. (Read more)

The government also decided to reallocate the remaining budget from Sihanoukville’s 34-road renovation project to upgrade the sidewalks along the Siem Reap River. Another separate US$9-million budget has also been reallocated to restore rainwater and sewage systems.

Siem Reap is one of the provinces that have high potential in Cambodia, into which the government has been putting continuous effort in enhancing infrastructure. In July this year, at least 20 major investment projects have almost been proposed as part of the 2020-2035 Siem Reap Tourism Development Masterplan.

- Video Advertisement -

Related Post

Japan-Funded 20,000-Hectare Southwest Phnom Penh Irrigation Scheme Nears 99% Completion

Inspected by Water Resources Minister Thor Chetha, the major JICA infrastructure project across Kampong Speu, Kandal, and Takeo promises to boost rice yields for nearly 8,000 farming families Agricultural productivity and flood management southwest of Cambodia’s capital are set for a major transformation as the Rehabilitation and Improvement of Irrigation and Drainage Systems Project in […]

Bassac and Prek Koy Riverbank Protection Projects Achieve 100% Completion Across Kandal and Kampong Cham

Cambodia’s water infrastructure development achieved a key milestone as two major riverbank protection projects along the Bassac River and Prek Koy stream reached 100% completion across Kandal and Kampong Cham provinces. An inter-ministerial working group led by HE Sot Rasmei, Secretary of State and Chairman of the Procurement Committee at the Ministry of Water Resources […]

Jinding Air Liquefaction Breaks Ground on $10 Million Industrial Gas Plant in Kampong Speu

Cambodia’s industrial supply chain achieved a major milestone with the official groundbreaking of the nation’s first large-scale industrial gas production facility in Kampong Speu province. Valued at over $10 million, the flagship project developed by Jinding Air Liquefaction (Cambodia) Co., Ltd. officially commenced construction on July 2, 2026, during a ceremony presided over by Kampong […]

Chip Mong Breaks Ground on $250 Million Food and Beverage Production Complex in Phnom Penh

Domestic manufacturing in Cambodia achieved a major milestone as local conglomerate Chip Mong officially broke ground on a state-of-the-art food and beverage production facility valued at over $250 million. The groundbreaking ceremony held on August 1, 2026, was presided over by Samdech Men Sam An, Privy Councillor to His Majesty the King, in Khan Dangkao, […]

Final Section of Cambodia’s National Road 5 Reaches Major Construction Milestone

Achieving over 63 percent completion, the vital Serei Sophorn to Poipet corridor paves the way for seamless international trade and regional connectivity by 2027 The ambitious transformation of Cambodia’s transport network is rapidly nearing its final triumph as the restoration and quality upgrade of National Road 5 enters its last leg. By the end of […]

The Bassac River Bridge Nears Spectacular Completion to Transform Phnom Penh Infrastructure

Phnom Penh is rapidly advancing toward an era of unprecedented urban connectivity as the highly anticipated Bassac River Bridge construction project charges toward its final phases. As of early July 2026, this iconic twin concrete bridge connecting Chak Angre Krom and Prek Pra has achieved a spectacular 79% completion rate. This major milestone was underscored […]