Three Sections of NR5 Expansion 90%, 23%, and 36% Complete, Respectively

To date, three sections of the National Road 5 (NR5) expansion project have on average reached approximately 50% completion and is scheduled to be complete by 2022.

According to the Ministry of Public Works and Transport’s report on 16 February, the progress of each section of road are as follows:

1. The northern part from Battambang to Serey Sophoan (84 km) is 89.75% complete and scheduled for completion in July 2021

2. The central section from Thla Ma Om to Battambang (146 km) is 23.02% completed and scheduled for completion in April 2022

3. The southern part from Prek Kdam in Kandal province to Thla Ma Om in Pursat province (135 km) is 35.62% completed and scheduled for completion in August 2022

The renovation of NR5 has a total length of 366km connecting the capital to the northwest part of the country passing through Kompong Chhnang, Pursat, Battambang, and Banteay Meanchey provinces.

The road will be upgraded to Asphalt Concrete (AC) and expanded to four lanes with a width of 23m. The project is being undertaken with a loan of US$500 million from the Japanese government.

- Video Advertisement -

Related Post

Construction of Bassac River Bridge Linking Chak Angre Krom and Prek Pra Reaches 73% Completion

The construction of the highly anticipated bridge across the Bassac River, connecting Chak Angre Krom to Prek Pra, has achieved a major milestone, reaching 73% completion by the end of May 2026. According to the inspection team on 01 June 2026, led by HE Soung Heng, Secretary of State and Project Director, to monitor the […]

Bakheng Water Treatment Plant Expansion Crosses Major Threshold to Secure Capital Clean Water Access

Phase Three Progress Surpasses Seventy % Mark as Cambodia Broadens Utility Infrastructure to Support Rapid Economic Growth The ongoing construction of the Bakheng Water Treatment Plant Phase Three has achieved a significant milestone, with the project now certified as more than 70 % complete. This infrastructure expansion is poised to critically enhance the water distribution […]

Takhmao City Wastewater Infrastructure Project Reaches One-Third Completion Milestone

The construction of the wastewater treatment system in Takhmao City, Kandal Province, has reached a significant milestone, achieving an overall progress of 33 percent as of the end of April 2026. This advancement was confirmed during a site visit on May 7, 2026, led by His Excellency Ros Vanna, Secretary of State of the Ministry […]

Cambodia and Japan Sign Consultancy Agreement for Koh Ksach Tonlea Bridge Project in Kandal Province

The Ministry of Public Works and Transport and the Japanese consortium CHODAI Co., LTD have formally signed a consulting services agreement for the Koh Ksach Tonlea Bridge construction project in Kandal Province. The signing ceremony took place on May 8, 2026, under the high presidency of His Excellency Peng Ponea, Minister of Public Works and […]

Japan Pledges $47 Million to Strengthen Flood Resilience and Wastewater Infrastructure in Phnom Penh

Japan has officially extended a $47 million credit facility to support a comprehensive flood protection and wastewater drainage development project in the Cambodian capital. This strategic funding follows a formal exchange of notes between the Royal Government of Cambodia and the government of Japan on April 23, 2026. The announcement was formalized during a recent […]

New $20 Million Cassava Processing Plant Breaks Ground in Kampong Speu to Boost Agri-Industrial Exports

The agricultural landscape of Cambodia reached a new milestone on the morning of April 27, 2026, as officials broke ground on a $20 Million cassava starch processing factory in Kampong Speu province. The ceremony, highlighted by the Ministry of Industry, Science, Technology, and Innovation, marks a pivotal advancement in the Kingdom’s efforts to move up […]