New US$900m Siem Reap Airport Aiming for 67% Completion in 2021

Angkor International Airport Investment (Cambodia) Co., Ltd. (AIAI) will accelerate the construction progress of the new Siem Reap International Airport, aiming for 67% completion by 2021, and full completion by 2023 as planned.

AIAI revealed this 2021 plan during a site inspection by Siem Reap Governor HE Tea Seiha on 06 February.

The company reported that by the end of 2020, the overall project was about 35% complete, 15% for the passenger terminal and 10% for the flying zone.

For 2021, the company has vowed to complete the construction of passenger terminal by 78%, 45% for the flying zones, and overall infrastructure of 50%.

AIAI has also provided assurances that flights will not cause negative impacts on Angkor Wat and the surrounding architecture. Moreover, the firm is also taking environmental factor into serious account while constructing the airport.

The new airport is located in South Nikom district, approximately 51km from Siem Reap downtown or 40km from Angkor Wat. The construction began on 15 March 2020 and is scheduled to be completed by 2023.

The airport is being built on a 700-hectare plot with a 1,000-hectare special economic zone with an investment of over US$900 million. (Read more)

- Video Advertisement -

Related Post

Final Section of Cambodia’s National Road 5 Reaches Major Construction Milestone

Achieving over 63 percent completion, the vital Serei Sophorn to Poipet corridor paves the way for seamless international trade and regional connectivity by 2027 The ambitious transformation of Cambodia’s transport network is rapidly nearing its final triumph as the restoration and quality upgrade of National Road 5 enters its last leg. By the end of […]

The Bassac River Bridge Nears Spectacular Completion to Transform Phnom Penh Infrastructure

Phnom Penh is rapidly advancing toward an era of unprecedented urban connectivity as the highly anticipated Bassac River Bridge construction project charges toward its final phases. As of early July 2026, this iconic twin concrete bridge connecting Chak Angre Krom and Prek Pra has achieved a spectacular 79% completion rate. This major milestone was underscored […]

A $117 Million Economic Lifeline: Prime Minister Hun Manet Inaugurates Newly Expanded National Road 7

The newly upgraded 4-lane highway connecting Skun and Kampong Cham town is projected to deliver a 15.27% economic return, slashing travel times and boosting agricultural trade… In a major boost to Cambodia’s internal logistics network, a vital 45.489-kilometer section of National Road 7 connecting the Skun roundabout to the Kizuna Bridge roundabout in Kampong Cham […]

Maritime Geopolitical Rivalry Intensifies as Vietnam Accelerates $4 Billion Deep Sea Port Project in the Far South

The massive infrastructure development on Hon Khoai Island serves as both an economic gateway for the Mekong Delta and a strategic maritime shield amid shifting regional dynamics Ho Chi Minh City: The geopolitical and trade landscape of Southeast Asia is entering a highly competitive phase as nations across the region race to build strategic advantages. […]

Field Assessments Underway for Kandal Province New Strategic Bridge

A joint delegation evaluates four potential sites for the Koh Khsach Tonlea crossing to enhance rural connectivity and market access In a significant step forward for Cambodia’s infrastructure development, a multi-institutional technical team has launched a comprehensive field survey to determine the optimal location for the upcoming Koh Khsach Tonlea Bridge project in Kandal Province. […]

Cambodia Completes Major Expansion of National Road 7 Connecting Skun and Kampong Cham

The $117 million infrastructure upgrade backed by China is set for an official inauguration by Prime Minister Hun Manet in July… The extensive upgrade of National Road 7, stretching over 45 kilometers to connect the hub of Skun with Kampong Cham town, has officially reached 100% completion. To mark this infrastructural milestone, a formal handover […]