Construction of 150MW Tatai Leu Hydropower Dam in Koh Kong 15% Complete 

Construction of the Tatai Leu Hydropower Dam in Koh Kong to date is approximately 15% complete according to the Koh Kong Provincial Administration on 17 August.

Located in Thma Bang district and Koh Kong district upstream along the Tatai River, the project is being implemented by Cambodia Upper Tatay Hydropower Co Ltd with a total investment of US$389 million.

The project received the green light from the Council of the Ministers in October 2020 with a concession period of 39 years. The construction of the dam will take four years to be completed while the firm will continue to operate it for 35 years. (Read more)

 

 

- Video Advertisement -

Related Post

Japan-Funded 20,000-Hectare Southwest Phnom Penh Irrigation Scheme Nears 99% Completion

Inspected by Water Resources Minister Thor Chetha, the major JICA infrastructure project across Kampong Speu, Kandal, and Takeo promises to boost rice yields for nearly 8,000 farming families Agricultural productivity and flood management southwest of Cambodia’s capital are set for a major transformation as the Rehabilitation and Improvement of Irrigation and Drainage Systems Project in […]

Bassac and Prek Koy Riverbank Protection Projects Achieve 100% Completion Across Kandal and Kampong Cham

Cambodia’s water infrastructure development achieved a key milestone as two major riverbank protection projects along the Bassac River and Prek Koy stream reached 100% completion across Kandal and Kampong Cham provinces. An inter-ministerial working group led by HE Sot Rasmei, Secretary of State and Chairman of the Procurement Committee at the Ministry of Water Resources […]

Jinding Air Liquefaction Breaks Ground on $10 Million Industrial Gas Plant in Kampong Speu

Cambodia’s industrial supply chain achieved a major milestone with the official groundbreaking of the nation’s first large-scale industrial gas production facility in Kampong Speu province. Valued at over $10 million, the flagship project developed by Jinding Air Liquefaction (Cambodia) Co., Ltd. officially commenced construction on July 2, 2026, during a ceremony presided over by Kampong […]

Chip Mong Breaks Ground on $250 Million Food and Beverage Production Complex in Phnom Penh

Domestic manufacturing in Cambodia achieved a major milestone as local conglomerate Chip Mong officially broke ground on a state-of-the-art food and beverage production facility valued at over $250 million. The groundbreaking ceremony held on August 1, 2026, was presided over by Samdech Men Sam An, Privy Councillor to His Majesty the King, in Khan Dangkao, […]

Final Section of Cambodia’s National Road 5 Reaches Major Construction Milestone

Achieving over 63 percent completion, the vital Serei Sophorn to Poipet corridor paves the way for seamless international trade and regional connectivity by 2027 The ambitious transformation of Cambodia’s transport network is rapidly nearing its final triumph as the restoration and quality upgrade of National Road 5 enters its last leg. By the end of […]

The Bassac River Bridge Nears Spectacular Completion to Transform Phnom Penh Infrastructure

Phnom Penh is rapidly advancing toward an era of unprecedented urban connectivity as the highly anticipated Bassac River Bridge construction project charges toward its final phases. As of early July 2026, this iconic twin concrete bridge connecting Chak Angre Krom and Prek Pra has achieved a spectacular 79% completion rate. This major milestone was underscored […]