Construction of Mekong River Bridge Linking Dei Edth and Thmor Kor Reaches Nearly Fifty Percent Completion

The construction of the strategic bridge spanning the Mekong River at the Dei Edth-Thmor Kor crossing has achieved significant momentum, with work now nearly halfway finished. Phorn Rim, a spokesperson for the Ministry of Public Works and Transport, confirmed on April 23, 2026, that the project has reached 47.6% completion as of April 22. This progress indicates that the development is currently moving 2.60 percent faster than originally projected in the master plan.

This vital infrastructure project was initiated during a joint groundbreaking ceremony for the bridge and the Phnom Penh-Bavet Expressway on June 7, 2023. The event was presided over by Samdech Techo Hun Sen, then Prime Minister and current President of the Senate, alongside former Chinese Ambassador to Cambodia, Wang Wentian. The project is considered a cornerstone of the Kingdom’s regional connectivity strategy (read more).

Spanning the river in Kandal province, the bridge connects the western bank in Dei Edth commune of Kien Svay district to the eastern bank in Thmor Kor commune of Lvea Em district. Once completed, it will serve as a crucial link for local transport and long-distance logistics, easing the flow of traffic between these two growing administrative zones and providing a necessary bypass for the capital.

In terms of technical specifications, the total length of the project is 3,700 meters. This includes the main bridge structure, which measures 1,600 meters in length and 26 meters in width, as well as connecting roads totaling 2,100 meters with a matching width of 26 meters. The entire development is being funded by a $230 million investment from the national budget.

The construction is being executed by the China Road and Bridge Corporation (CRBC), with technical supervision provided by the Guangzhou Wanan Construction Supervision Co., Ltd. With an established construction timeframe of 37 months, the project continues to advance efficiently toward its goal of enhancing Cambodia’s national road network and supporting the nation’s economic growth.

- Video Advertisement -

Related Post

Final Section of Cambodia’s National Road 5 Reaches Major Construction Milestone

Achieving over 63 percent completion, the vital Serei Sophorn to Poipet corridor paves the way for seamless international trade and regional connectivity by 2027 The ambitious transformation of Cambodia’s transport network is rapidly nearing its final triumph as the restoration and quality upgrade of National Road 5 enters its last leg. By the end of […]

The Bassac River Bridge Nears Spectacular Completion to Transform Phnom Penh Infrastructure

Phnom Penh is rapidly advancing toward an era of unprecedented urban connectivity as the highly anticipated Bassac River Bridge construction project charges toward its final phases. As of early July 2026, this iconic twin concrete bridge connecting Chak Angre Krom and Prek Pra has achieved a spectacular 79% completion rate. This major milestone was underscored […]

A $117 Million Economic Lifeline: Prime Minister Hun Manet Inaugurates Newly Expanded National Road 7

The newly upgraded 4-lane highway connecting Skun and Kampong Cham town is projected to deliver a 15.27% economic return, slashing travel times and boosting agricultural trade… In a major boost to Cambodia’s internal logistics network, a vital 45.489-kilometer section of National Road 7 connecting the Skun roundabout to the Kizuna Bridge roundabout in Kampong Cham […]

Maritime Geopolitical Rivalry Intensifies as Vietnam Accelerates $4 Billion Deep Sea Port Project in the Far South

The massive infrastructure development on Hon Khoai Island serves as both an economic gateway for the Mekong Delta and a strategic maritime shield amid shifting regional dynamics Ho Chi Minh City: The geopolitical and trade landscape of Southeast Asia is entering a highly competitive phase as nations across the region race to build strategic advantages. […]

Field Assessments Underway for Kandal Province New Strategic Bridge

A joint delegation evaluates four potential sites for the Koh Khsach Tonlea crossing to enhance rural connectivity and market access In a significant step forward for Cambodia’s infrastructure development, a multi-institutional technical team has launched a comprehensive field survey to determine the optimal location for the upcoming Koh Khsach Tonlea Bridge project in Kandal Province. […]

Cambodia Completes Major Expansion of National Road 7 Connecting Skun and Kampong Cham

The $117 million infrastructure upgrade backed by China is set for an official inauguration by Prime Minister Hun Manet in July… The extensive upgrade of National Road 7, stretching over 45 kilometers to connect the hub of Skun with Kampong Cham town, has officially reached 100% completion. To mark this infrastructural milestone, a formal handover […]