NR2 & 22 Construction Poor Quality; MPTW Orders Urgent Fix & Sets Deadline for August

The Ministry of Public Works and Transport (MPWT) has found that some parts of the construction of NR2 and NR22 are poor in quality and lack technical standards while instructing the restricting construction companies to fix them immediately and finish the whole project by August 2022.

According to the site inspection of MPWT Minister HE Sun Chanthol, as of April 25, the construction has achieved 76.20%, far slower than scheduled with many delays.

“The construction of this road was slow because the construction company did not have enough machinery and manpower, not due to the pandemic, as claimed by the company,” said HE Sun Chanthol.

“After testing, we also found some parts are of poor quality. Thus, we told the construction firm to fix it and set an overall completion deadline for August. In August, the roads must be completed with contracted quality, or otherwise, the ministry will not accept it,” he added.

NR2 has a total length of 62.56 km from Takhmao roundabout to Daun Keo roundabout in Takeo province and NR22 has a total length of 9.61 km from Daun Keo roundabout to Ang Ta Som, NR3. (Read more)

With ground broken in early 2020, both projects are being built under a US$56 million budget, which is jointly financed by the South Korean government and Cambodian government budget.

Construction is being done by Hasan Engineering & Constructions Co., Ltd and technical inspection by Dasan Constructions Co., Ltd, Dong II Engineering Consultants Co., Ltd and Seoyoung Engineering Co., Ltd Join Venture.

- Video Advertisement -

Related Post

MPWT and AIIB Review Feasibility Study for National Road 8 Upgrade Connecting Prek Tamak to Ponhea Kraek

High-level technical session examines environmental-social assessments and financial modeling to accelerate a critical transit corridor across eastern Cambodia Phnom Penh: Upgrading Cambodia’s strategic transport corridors gained momentum as government officials and international financial partners reviewed preliminary engineering and environmental evaluations for a vital regional thoroughfare on National Route 8. According to the meeting session on […]

Prime Minister Inaugurates 98-Kilometer Road Network Worth Nearly $44 Million in Northeastern Cambodia

Modernizing National Road 73 alongside Provincial Roads 377 and 377A, the $43.95 million project enhances climate resilience, boosts agro-logistics, and strengthens trade routes across Kratie and Tboung Khmum. In a major boost to northeastern Cambodia’s transport networks, Prime Minister Samdech Thipadei Hun Manet officially inaugurated three upgraded national and provincial road sections in Kratie and […]

Cambodia Advances Strategic Infrastructure Plan with Upgraded National Road 1 and New Mekong River Bridge

Discussions on JICA’s draft final report highlight a 53-kilometer road widening project and an Extradosed Bridge connecting Phnom Penh to Areyksat along the Southern Economic Corridor As Southeast Asian nations continuously upgrade their transport networks to drive economic integration and regional competitiveness, Cambodia is taking significant strides to modernize its core transit corridors. On Wednesday, […]

National Road 7 Expansion Project Nears Completion as Vital Economic Link Reaches 90% Finish

Accelerated construction on the Skun to Kampong Cham corridor aims for early delivery to boost regional trade and transport efficiency The expansion and upgrade of National Road 7, a critical infrastructure project connecting the Skun area to Kampong Cham city, has reached nearly 90% completion as of March 2026. This significant milestone was highlighted by […]

Cambodia Road Network Expands to Over 20,000 Kilometers in 2025

Strategic infrastructure development adds 426 kilometers to the national network to boost logistics and economic growth The total length of developed roads in Cambodia reached 20,733.91 kilometers by the end of 2025, marking a notable increase of approximately 426.32 kilometers compared to the previous year. This data was highlighted in the 2025 Annual Progress Report […]

Cambodia and Laos to Fast-Track Cross-Border Connectivity with New Ratanakiri-Attapeu Road Link

Joint inspection team to finalize construction zones this February to unlock new trade and economic opportunities Cambodia and Laos have reached a pivotal agreement to conduct a joint technical inspection aimed at defining the specific zones for a new road project connecting Ratanakiri province in Cambodia to Attapeu province in Laos. This initiative is a […]