Construction of Monivong Flyover Pillars 11% Complete

The construction of the Preah Monivong flyover, the first circular flyover in Cambodia, has been 11% completed as the technical team is currently drilling 219 pillars on Samdech Techo Hun Sen Blvd and Preah Monivong Blvd. 

Mr Sam Piseth, Director of the Department of Public Works and Transport of Phnom Penh, told BTV on 7 February that the construction company is currently drilling the foundation of the Preah Monivong flyover. To date, 25 pillars have been drilled, which is 11.41% of the total. 

The NR1 zone of the project, which is the area around Hun Sen Blvd, is going smoothly. However, the NR2 zone faces difficulties due to some protests. 

In the N3 zone along Preah Monivong Blvd, three foundations have been drilled, while the rest will be done after the impact resettlement. However, the work on St. 271 has yet to start. 

The Preah Monivong flyover is being built by OCIC at a cost of more than US$36 million and will take 36 months to be completed. It is located at the intersection of Samdech Techo Hun Sen Blvd., Monivong Blvd. and St. 217 in Khan Chamkarmon and Khan Meanchey. (Read more)

 

 

- Video Advertisement -

Related Post

Japan-Funded 20,000-Hectare Southwest Phnom Penh Irrigation Scheme Nears 99% Completion

Inspected by Water Resources Minister Thor Chetha, the major JICA infrastructure project across Kampong Speu, Kandal, and Takeo promises to boost rice yields for nearly 8,000 farming families Agricultural productivity and flood management southwest of Cambodia’s capital are set for a major transformation as the Rehabilitation and Improvement of Irrigation and Drainage Systems Project in […]

Bassac and Prek Koy Riverbank Protection Projects Achieve 100% Completion Across Kandal and Kampong Cham

Cambodia’s water infrastructure development achieved a key milestone as two major riverbank protection projects along the Bassac River and Prek Koy stream reached 100% completion across Kandal and Kampong Cham provinces. An inter-ministerial working group led by HE Sot Rasmei, Secretary of State and Chairman of the Procurement Committee at the Ministry of Water Resources […]

Jinding Air Liquefaction Breaks Ground on $10 Million Industrial Gas Plant in Kampong Speu

Cambodia’s industrial supply chain achieved a major milestone with the official groundbreaking of the nation’s first large-scale industrial gas production facility in Kampong Speu province. Valued at over $10 million, the flagship project developed by Jinding Air Liquefaction (Cambodia) Co., Ltd. officially commenced construction on July 2, 2026, during a ceremony presided over by Kampong […]

Chip Mong Breaks Ground on $250 Million Food and Beverage Production Complex in Phnom Penh

Domestic manufacturing in Cambodia achieved a major milestone as local conglomerate Chip Mong officially broke ground on a state-of-the-art food and beverage production facility valued at over $250 million. The groundbreaking ceremony held on August 1, 2026, was presided over by Samdech Men Sam An, Privy Councillor to His Majesty the King, in Khan Dangkao, […]

Final Section of Cambodia’s National Road 5 Reaches Major Construction Milestone

Achieving over 63 percent completion, the vital Serei Sophorn to Poipet corridor paves the way for seamless international trade and regional connectivity by 2027 The ambitious transformation of Cambodia’s transport network is rapidly nearing its final triumph as the restoration and quality upgrade of National Road 5 enters its last leg. By the end of […]

The Bassac River Bridge Nears Spectacular Completion to Transform Phnom Penh Infrastructure

Phnom Penh is rapidly advancing toward an era of unprecedented urban connectivity as the highly anticipated Bassac River Bridge construction project charges toward its final phases. As of early July 2026, this iconic twin concrete bridge connecting Chak Angre Krom and Prek Pra has achieved a spectacular 79% completion rate. This major milestone was underscored […]