Construction of NR10 Connecting Koh Kong to Battambang 70% Complete

The construction of NR10 connecting from Battambang to Koh Kong has been 69.28% completed as of January and it is scheduled to be completed by the end of 2024, according to a press conference by the Battambang Provincial Administration on 24 January. 

NR10 has a total length of more than 197 kilometres and the construction will cost a total of US$188 million, via funding from the Chinese government. 

Battambang Provincial Governor Sok Loo said this road will be an important road to facilitate transportation within the country and with neighbouring countries. 

The construction of NR10 began in March 2020 under the auspices of Prime Minister Samdech Hun Sen and Chinese Ambassador HE Wang Wentian. (Read more)

 

- Video Advertisement -

Related Post

Battambang Launches Strategic Urban Infrastructure Project on Street 154

Extensive road expansion and drainage system upgrades in Wat Kor Sangkat signal the start of a city-wide modernization initiative The Battambang Provincial Administration has officially broken ground on a comprehensive infrastructure project in Battambang City, focusing on road restoration and the construction of advanced drainage systems. The ceremony, held on March 9, 2026, was led […]

Cambodia and South Korea Explore Small-Scale Hydropower Potential at Dauntri and Reaksa Reservoirs

Joint feasibility study focuses on integrating renewable energy and solar power to secure sustainable water and electricity supplies for local communities The Ministry of Water Resources and Meteorology has partnered with the Korea Water Resources Corporation, known as K-water, to conduct a comprehensive feasibility study on the installation of small-scale hydropower facilities at the Dauntri […]

Borey Peng Huoth Announces Exclusive Pre-Sale Event for New Phum Nimith Project in Chbar Ampov

Early access to prime locations within the prestigious Grand Star Platinum development starting this March Following the successful groundbreaking ceremony held on January 30, 2026, Borey Peng Huoth is pleased to announce the official pre-sale launch of its newest residential development, Phum Nimith. This highly anticipated event will take place over three days from March […]

Accelerating Connectivity: Mekong River Bridge Connecting Dei Edth-Thmor Kor Surpasses 35% Completion

Minister Peng Ponea inspects the strategic infrastructure project in Kandal province to ensure rigorous technical standards and timely delivery for the public The construction of the major bridge across the Mekong River Dei Edth-Thmor Kor connecting Dei Edth commune in Kien Svay district to Thmor Kor commune in Lvea Em district has reached a significant […]

Cambodia and Laos to Fast-Track Cross-Border Connectivity with New Ratanakiri-Attapeu Road Link

Joint inspection team to finalize construction zones this February to unlock new trade and economic opportunities Cambodia and Laos have reached a pivotal agreement to conduct a joint technical inspection aimed at defining the specific zones for a new road project connecting Ratanakiri province in Cambodia to Attapeu province in Laos. This initiative is a […]

Kratie City Drainage and Pumping Station Project Surpasses 68% Completion

Provincial authorities and ADB-funded initiative accelerate infrastructure development to eliminate seasonal flooding and boost local economic appeal Kratie City is undergoing a significant infrastructural transformation as the construction of its comprehensive drainage network and rainwater pumping station reaches 68 percent completion. This development is a key sub-project of the Fourth Greater Mekong Subregion Corridor Towns […]