Bassac River’s Seventh Bridge Crosses 85% Completion Mark Ahead of Schedule

Construction on the seventh bridge spanning the Bassac River, connecting Chak Angre Krom and Prek Pra in southern Phnom Penh, reached 85% completion as of early September 2026. The progress milestone was confirmed during an on-site project inspection led by H.E. Soung Heng, Secretary of State and Project Director at the Ministry of Public Works and Transport, on September 8, 2026. Since breaking ground on February 19, 2024, the strategic infrastructure development has progressed smoothly, tracking 3.22% ahead of its master schedule.

A comprehensive technical evaluation indicates that the bridge’s foundation, lower substructure, and connecting upper bridge structures are all 100 % complete. At the same time, construction of the main bridge superstructure has reached 84.6 % completion. Surrounding road network integration stands at 51 % overall, with both the 804.30-meter connecting road and the 1,541-meter access ramps passing the 50 % mark.

During the inspection, project managers commended contractor Shanghai Construction Group for upholding technical standards, contractual commitments, and structural aesthetics. Due to rising water levels during the peak monsoon season, the Ministry instructed the contractor to step up site safety protocols and install extra water safety buoys and cushions to protect river traffic throughout the remaining construction phase. Engineering teams estimate that the final bridge sections will connect across the Bassac River by late 2026, with full project completion anticipated by mid-2027.

Designed to alleviate chronic traffic congestion across the capital’s southern corridors, the four-lane crossing serves as a key urban transport link. It represents the fourth major river bridge following the Koh Norea, Preah Monivong, and Koh Anlong Chen bridges connecting to Xi Jinping Boulevard. Once fully operational, the new route will streamline travel between Meanchey and Chbar Ampov districts, enhance trade movement, and improve urban mobility for Phnom Penh commuters. (read more)

- Video Advertisement -

Related Post

Cambodia’s Transport Ministry and JICA Assess Mekong Riverbank Erosion Threatening Tsubasa Bridge Infrastructure

Technical experts evaluate riverbed scouring and shoreline collapse near Neak Loeung to formulate long-term protective engineering measures Phnom Penh: Hydrological shifts and riverbank erosion along the Mekong River continue to pose structural challenges to major transportation infrastructure in Cambodia. On September 2, 2026, Director General of Public Works H.E. Heng Rathpiseth chaired a technical session […]

The Bassac River Bridge Nears Spectacular Completion to Transform Phnom Penh Infrastructure

Phnom Penh is rapidly advancing toward an era of unprecedented urban connectivity as the highly anticipated Bassac River Bridge construction project charges toward its final phases. As of early July 2026, this iconic twin concrete bridge connecting Chak Angre Krom and Prek Pra has achieved a spectacular 79% completion rate. This major milestone was underscored […]

Field Assessments Underway for Kandal Province New Strategic Bridge

A joint delegation evaluates four potential sites for the Koh Khsach Tonlea crossing to enhance rural connectivity and market access In a significant step forward for Cambodia’s infrastructure development, a multi-institutional technical team has launched a comprehensive field survey to determine the optimal location for the upcoming Koh Khsach Tonlea Bridge project in Kandal Province. […]

Ministry of Public Works Advances Plans for New Mekong River Bridge Connecting Koh Norea and Arey Ksat

Technical designs and connecting roads were evaluated in a high-level meeting with TP Moral Group and OCIC to enhance regional infrastructure The Ministry of Public Works and Transport has advanced discussions on major infrastructure development with a high-level meeting dedicated to evaluating the study and construction project of a new bridge crossing the Mekong River. […]

Construction of Bassac River Bridge Linking Chak Angre Krom and Prek Pra Reaches 73% Completion

The construction of the highly anticipated bridge across the Bassac River, connecting Chak Angre Krom to Prek Pra, has achieved a major milestone, reaching 73% completion by the end of May 2026. According to the inspection team on 01 June 2026, led by HE Soung Heng, Secretary of State and Project Director, to monitor the […]

New Bassac River Crossing Surpasses 68% Completion as Project Moves Ahead of Schedule

The construction of the Bassac River Bridge connecting Chak Angre Krom and Prek Pra has entered a high-velocity phase, with total progress reaching approximately 68% as of April 20, 2026. According to Phon Rim, spokesperson for the Ministry of Public Works and Transport, the strategic infrastructure project is currently 6% ahead of its original development […]