Nine Infrastructure Projects Prioritised in Phnom Penh Development Masterplan 2035

According to Sub-decree 181 regarding the Phnom Penh land-use masterplan from 2015 to 2035, nine infrastructure development plans and policies have been put on the priority list. To date, some have been implemented, while others have not.

Below are the progresses of each development plan:

1) Roads, railways, and drainage system improvement
The plan has been gradually implemented. For instance, a new draft sub-decree on the management of land, roads, and railways is now being prepared by the Ministry of Public Works and Transport (MPWT). Besides, the MPWT is also working on drafting a new law on wastewater and sewage systems (Read more and more)

2) Cargo train stations and dry ports in Pou Senchey District
Based on the information obtained by the Construction & Property Magazine as of 9 July, there has been no update revealed by the officials regarding this project.

3) Phnom Phnom Penh-Ho Chi Minh Railway Project
According to the initial study, the project will include constructions of a bridge crossing the Mekong River in Phnom Penh and a railway connecting the Samraong station to Phnom Penh southern suburbs crossing the Bassac River. The government has recently claimed that the feasibility studies for this project will be conducted after the Phnom Penh-Bavet expressway project. (Read more)

4) Phnom Penh International Airport Expansion
Not only expanding the current airport, but the government has also allowed a private firm to construct a new international airport in Kandal province, which to date is been over 40% complete and scheduled to open by 2023. (Read more)

5) Bassac River bank improvement
There have been thus far several projects implemented since 2015. For instance, in March, the Chbar Ampov District Administration has revealed plans to build a new river frontage road and a stretch of riverbank on the eastern side of the Bassac River from the base of the Old Monivong Bridge to the Koh Norea Development Zone. (Read more)

6) Establishment regulations for high-rise buildings
According to the plan, these regulations will be set for areas including Chbar Ampov, Boeung Krapeu, Boeung Paung Peay, and Boeung Kak. However, based on the information obtained by the Construction & Property Magazine as of 9 July, there has been no update revealed by the officials regarding this project.

7) Landfills and waste management improvement
This project will be implemented by encouraging more private investment in waste processing plants and landfills in Phnom Penh. According to the municipality, several proposals have been raised.

In March 2020, the Ministry of Mines and Energy unveiled a plan to develop a waste-to-energy power plant. The project is a collaboration between ADB and the Infrastructure of Asia of Singapore. (Read more)

In early 2021, the Ministry of Environment (MoE) also requested two Singaporean firms, Infrastructure Asia (IA) and Singapore Corporation Enterprise (SCE), to develop a master plan for a new landfill project in Phnom Penh. (Read more)

8) Setting up Prek Pnov Ecological Zone
The project will be implemented on a 75-hectare land plot Boeung Ta Mok lake in Prek Pnov district. To date, over 100,000 trees are being planted in the area. The project will also include the construction of other amenities such as a swimming pool, a recreation area, shops, restaurants and an amusement park for people to relax. The project is scheduled for completion by 2023. (Read more)

9) Establishment of a historic center in Phnom Penh

Based on the information obtained by the Construction & Property Magazine as of 9 July, there has been no update revealed by the officials regarding this project.

Nevertheless, this master plan is subjected to change or revision every 5 years if necessary for economic and social development.

- Video Advertisement -

Related Post

Cambodia Completes Major Expansion of National Road 7 Connecting Skun and Kampong Cham

The $117 million infrastructure upgrade backed by China is set for an official inauguration by Prime Minister Hun Manet in July… The extensive upgrade of National Road 7, stretching over 45 kilometers to connect the hub of Skun with Kampong Cham town, has officially reached 100% completion. To mark this infrastructural milestone, a formal handover […]

Cambodia to Upgrade National Road 4 Section in Chbar Mon to Drive Regional Economic Growth

The Kampong Speu Provincial Administration recently announced a comprehensive infrastructure initiative aimed at upgrading the aesthetics and functionality of a key section of National Road 4 within Chbar Mon City. The project is strategically designed to transform the province into a vital economic and commercial center for the region. This development plan was detailed in […]

Bassac Riverbank Stabilization Project in Kandal Reaches 60% Completion

The ongoing infrastructure initiative to reinforce the Bassac riverbank in Sampov Poun City, Kandal Province, has achieved a significant milestone, with construction teams completing approximately 60% of the designated works. Local authorities and engineering crews remain heavily committed to accelerating the remaining phases to ensure the project concludes entirely on schedule. During a recent field […]

Cambodia and Vietnam Partner to Build Major Drug Rehabilitation Center in Svay Rieng

Cambodia and Vietnam are joining forces to establish an expansive National Drug Treatment and Rehabilitation Center in Svay Rieng Province. The planned facility will cover more than fifty-three hectares of land, marking a significant step forward in bilateral efforts to address substance dependency and long-term recovery. The project advanced further following a strategic meeting on […]

Cambodia Nears Completion of Strategic Border Ring Road in Northeastern Provinces

Funded by the Border Infrastructure Fund, the infrastructure project in Mondulkiri and Ratanakiri achieves over 95% of its construction targets Cambodia’s ambitious infrastructure initiative to establish a continuous border ring road is nearing full completion, with construction teams successfully executing the vast majority of planned developments in Mondulkiri and Ratanakiri provinces. From the commencement of […]

Construction of Bassac River Bridge Linking Chak Angre Krom and Prek Pra Reaches 73% Completion

The construction of the highly anticipated bridge across the Bassac River, connecting Chak Angre Krom to Prek Pra, has achieved a major milestone, reaching 73% completion by the end of May 2026. According to the inspection team on 01 June 2026, led by HE Soung Heng, Secretary of State and Project Director, to monitor the […]