Transport Minister Urges Construction Firm to Finish Kampot Tourism Port by June

Minister of Public Works and Transport HE Sun Chanthol has ordered the responsible firm to finish Kampot Tourism Port’s construction by June 2021 after several delays.

HE Sun Chanthol said during the site inspection on 04 January that the company should set a concrete plan or add more labour to accelerate the construction speed and to ensure that it proceeds as scheduled.

“It is not good to delay the construction. The Ministry of Tourism is not happy, and ADB is also not happy. Therefore, the firm must follow the contract and properly finish the construction with the promised quality by June,” said HE Sun.

The firm has accepted the request and reported that the construction is now 45% completed, with the structure scheduled for April.

HE Sun Chanthol’s order comes after the temporary halt in construction procedure due to the COVID-19 crisis, which caused construction delays several times. (Read more and more)

Located in Toek Chhu district, the ground was broken on the project in August 2018 and is being built under an US$8 million loan from the Asia Development Bank (ABD). (Read more)

Once operational, the 300-metre-long port will allow the docking of tourism vessels, which can carry up to 300 to 400 passengers.

The Kampot international tourism seaport will be the main gateway connecting tourism vessels from Thailand and Vietnam to Cambodia’s Kampot province.

- Video Advertisement -

Related Post

Final Section of Cambodia’s National Road 5 Reaches Major Construction Milestone

Achieving over 63 percent completion, the vital Serei Sophorn to Poipet corridor paves the way for seamless international trade and regional connectivity by 2027 The ambitious transformation of Cambodia’s transport network is rapidly nearing its final triumph as the restoration and quality upgrade of National Road 5 enters its last leg. By the end of […]

The Bassac River Bridge Nears Spectacular Completion to Transform Phnom Penh Infrastructure

Phnom Penh is rapidly advancing toward an era of unprecedented urban connectivity as the highly anticipated Bassac River Bridge construction project charges toward its final phases. As of early July 2026, this iconic twin concrete bridge connecting Chak Angre Krom and Prek Pra has achieved a spectacular 79% completion rate. This major milestone was underscored […]

A $117 Million Economic Lifeline: Prime Minister Hun Manet Inaugurates Newly Expanded National Road 7

The newly upgraded 4-lane highway connecting Skun and Kampong Cham town is projected to deliver a 15.27% economic return, slashing travel times and boosting agricultural trade… In a major boost to Cambodia’s internal logistics network, a vital 45.489-kilometer section of National Road 7 connecting the Skun roundabout to the Kizuna Bridge roundabout in Kampong Cham […]

Maritime Geopolitical Rivalry Intensifies as Vietnam Accelerates $4 Billion Deep Sea Port Project in the Far South

The massive infrastructure development on Hon Khoai Island serves as both an economic gateway for the Mekong Delta and a strategic maritime shield amid shifting regional dynamics Ho Chi Minh City: The geopolitical and trade landscape of Southeast Asia is entering a highly competitive phase as nations across the region race to build strategic advantages. […]

Field Assessments Underway for Kandal Province New Strategic Bridge

A joint delegation evaluates four potential sites for the Koh Khsach Tonlea crossing to enhance rural connectivity and market access In a significant step forward for Cambodia’s infrastructure development, a multi-institutional technical team has launched a comprehensive field survey to determine the optimal location for the upcoming Koh Khsach Tonlea Bridge project in Kandal Province. […]

Cambodia Completes Major Expansion of National Road 7 Connecting Skun and Kampong Cham

The $117 million infrastructure upgrade backed by China is set for an official inauguration by Prime Minister Hun Manet in July… The extensive upgrade of National Road 7, stretching over 45 kilometers to connect the hub of Skun with Kampong Cham town, has officially reached 100% completion. To mark this infrastructural milestone, a formal handover […]