Khmer-Thai Stueng Bat International Border Checkpoint Nears Completion Despite Delays

The construction of the Stueng Bat-Ban Nong Ean border checkpoint, a joint project between the governments of Cambodia and Thailand, is nearing completion, according to a recent site inspection by His Excellency Minister Sun Chanthol, Minister of Public Works and Transport. As of March 20, 2023, the project was reported to be 82% complete, with a scheduled completion date of May 2023.

However, HE Sun Chanthol expressed concerns that further delays may occur due to budget cuts by the Thai side.

“The company said that the project was 82 percent completed and was scheduled to be completed in May, which was delayed because the Thai side reduced the budget by only 40 percent … But when we came to check, we found that May is not yet, even if he (the construction company) has enough money …,” said HE minister.

The Stueng Bat-Ban Nong Ean border checkpoint aims to alleviate traffic congestion at the Poipet border gate, which is the largest and most important traffic flow between Cambodia and Thailand. The project has already been delayed twice and is being constructed with a concessional loan of approximately 26.5 million US dollars.

“This project has already been postponed twice, the first time, more than 100 days, the second time, more than 200 days. Now they want to extend it for another 3-4 days, we can postpone it, but it depends on the contract” HE added.

The Ministry of Public Works and Transport will discuss with the Thai side to speed up the process of lowering the budget for construction companies to be able to complete the project as planned.

Despite the delays, the Stueng Bat-Ban Nong Ean border checkpoint remains a vital project for both countries, and its completion will greatly benefit the flow of trade and tourism between Cambodia and Thailand.

(Read more)

- Video Advertisement -

Related Post

A $117 Million Economic Lifeline: Prime Minister Hun Manet Inaugurates Newly Expanded National Road 7

The newly upgraded 4-lane highway connecting Skun and Kampong Cham town is projected to deliver a 15.27% economic return, slashing travel times and boosting agricultural trade… In a major boost to Cambodia’s internal logistics network, a vital 45.489-kilometer section of National Road 7 connecting the Skun roundabout to the Kizuna Bridge roundabout in Kampong Cham […]

Maritime Geopolitical Rivalry Intensifies as Vietnam Accelerates $4 Billion Deep Sea Port Project in the Far South

The massive infrastructure development on Hon Khoai Island serves as both an economic gateway for the Mekong Delta and a strategic maritime shield amid shifting regional dynamics Ho Chi Minh City: The geopolitical and trade landscape of Southeast Asia is entering a highly competitive phase as nations across the region race to build strategic advantages. […]

Field Assessments Underway for Kandal Province New Strategic Bridge

A joint delegation evaluates four potential sites for the Koh Khsach Tonlea crossing to enhance rural connectivity and market access In a significant step forward for Cambodia’s infrastructure development, a multi-institutional technical team has launched a comprehensive field survey to determine the optimal location for the upcoming Koh Khsach Tonlea Bridge project in Kandal Province. […]

Cambodia Completes Major Expansion of National Road 7 Connecting Skun and Kampong Cham

The $117 million infrastructure upgrade backed by China is set for an official inauguration by Prime Minister Hun Manet in July… The extensive upgrade of National Road 7, stretching over 45 kilometers to connect the hub of Skun with Kampong Cham town, has officially reached 100% completion. To mark this infrastructural milestone, a formal handover […]

Cambodia to Upgrade National Road 4 Section in Chbar Mon to Drive Regional Economic Growth

The Kampong Speu Provincial Administration recently announced a comprehensive infrastructure initiative aimed at upgrading the aesthetics and functionality of a key section of National Road 4 within Chbar Mon City. The project is strategically designed to transform the province into a vital economic and commercial center for the region. This development plan was detailed in […]

Bassac Riverbank Stabilization Project in Kandal Reaches 60% Completion

The ongoing infrastructure initiative to reinforce the Bassac riverbank in Sampov Poun City, Kandal Province, has achieved a significant milestone, with construction teams completing approximately 60% of the designated works. Local authorities and engineering crews remain heavily committed to accelerating the remaining phases to ensure the project concludes entirely on schedule. During a recent field […]